Episode Overview
Every major capital project team will tell you they have a stage gate process. Iwona Wilson’s argument is that having the process and having the capability to use it are two completely different things, and that the distance between them is where billion-dollar surprises come from. She spent the first part of her career auditing projects for compliance and watching compliant projects fail anyway; then eleven years on the owner side at one of Australia’s largest energy producers, designing and teaching the decision gate process and facilitating the opportunity framing workshops that happen before anyone calls it a project. In this conversation she gives a complete 101 on phases and gates, explains why the final investment decision is the wrong place to look for leverage, walks through the six dimensions of decision quality and the one that always fails, and makes the case that the messy, uncomfortable middle of a framing workshop is not a process failure but the price of alignment.
A process is not a capability
Phases, gates, templates and mandatory checklists are an approval system. Framing opportunities, naming and challenging assumptions, aligning functions and measuring decision quality are a decision-making system. Most organizations have built the first and assume they bought the second.
Quality auditor turned framing facilitator
Iwona came into capital projects through ISO 9001 quality assurance at MW Kellogg and Foster Wheeler, then spent eleven years at Woodside Energy in Perth as an opportunity framing facilitator, trainer and project advisor. Since 2021 she has run Wilson Biz Consulting out of Houston.
The one skill for the next generation
A 34-minute companion episode on critical thinking as the skill that survives AI, where students should go to build it, and why Iwona thinks belief and detachment belong in the same conversation as decision analysis.
Every quotation here is Iwona Wilson’s or Orion Matthews’ own on-the-record words from the recorded conversation, lightly condensed for readability with meaning untouched. Timestamps are approximate and refer to positions in the full recording, which was published as an edited main episode plus a bonus episode, so a quote’s clock position in the brief will not always match the published cut. Career facts, dates, employers and locations come only from Iwona’s public LinkedIn profile and what she said on air; she speaks in a personal capacity. Chapter titles and the chapter map are editorial. Where an on-air figure was cited from memory, it is labelled as directional rather than repeated as fact. Banner photographs are open-licensed historic images of oil, gas and process plants, used illustratively: they are not the projects discussed; full credits are in Bookshelf & Links.
Episode Timeline
The conversation as it actually unfolded: ten chapters across roughly 81 minutes of on-the-record material, mapped against the show’s four-act structure. Click any block to jump to its chapter. The final block sits apart: it is the exchange the episode takes its title from, recorded after the formal wrap and carried into the published episode.
Act II is almost the whole episode. This is a teaching conversation more than an interview: the single longest stretch is the seventeen minutes on opportunity framing and the groan zone.
The Quality Route In
The welcome, and how a master’s thesis on brewery quality management became a career in billion-dollar capital projects.
Decision Gate 101
Phases and gates end to end: assess, concept, develop, FID, execute, and the post-investment review nobody talks about.
Compliance Isn’t Confidence
Years of audit reports on compliant projects that failed anyway, and the move to the owner side to find out why.
From Deliverables to Decisions
The mindset shift that changes what a team is asked to produce, the minimum-work question, and the two decisions at every gate.
Where Projects Are Won or Lost
Why FID is the wrong place to look for leverage, told through a family deciding whether to move to Florida.
When Gate Reviews Become Theater
The warning signs an executive can watch for from the back of the room, and what a lessons-learned sweep of your own process turns up.
The Groan Zone
Why traditional meetings can’t frame a complex opportunity, the neutral facilitator’s job, Post-it notes at the kitchen table, and Challenger.
Six Dimensions of Decision Quality
The decision quality wheel, walked through one dimension at a time, and the weakest-link rule that governs all six.
The Takeaway & the Billion-Dollar Math
Language fluency as the goal, and Orion puts a number on what bad decision-making costs a billion-dollar portfolio.
The Capability Gap
The exchange the episode is named for: everyone has a stage gate, so why the billion-dollar surprises? Plus the two failure modes at either end of process maturity.
Who carried the mic
Perfectly even turn-taking, heavily guest-weighted in volume: 166 speaker turns, and Iwona’s longest single answer runs over 800 words. Measured across the full recorded conversation.
The Guest · Iwona Wilson
Iwona Wilson came into capital projects sideways: through quality. Born and raised in Poland, she took a master’s in economics and engineering at Wrocław University of Economics and Business with a major in quality assurance, and wrote her thesis on installing a food quality management system in a London brewery. A chance encounter at the Institute of Quality Assurance in London led to a graduate place at MW Kellogg (now KBR), then quality assurance engineering at Foster Wheeler on FEED and EPCm work for ExxonMobil, Statoil and Sasol across the UK and Norway. In 2010 she crossed to the owner side, spending eleven years at Woodside Energy in Perth as an opportunity framing facilitator, trainer and project advisor, designing and teaching the decision gate process, and becoming the business’s subject-matter expert on professional facilitation. Since 2021 she has co-founded and run Wilson Biz Consulting from Houston, where she facilitates framing workshops for owner teams, implements decision gate process, and teaches a live Decision Gate Cohort.
“Capital projects are won or lost before they even begin. Most projects don’t fail because teams can’t execute. They fail because the problem was never clearly defined, stakeholders aligned too late, risks surfaced after commitment, and decisions rested on untested assumptions. I was always the person in the room asking the uncomfortable questions early, the thinker among the doers.”Iwona Wilson · from her public LinkedIn profile
Career journey
At Wilson Biz Consulting
- The remit
- Helping owners and leadership teams on complex projects strengthen early-stage framing, alignment and governance, through facilitated workshops and summits, project governance implementation, and training in front-end loading, stage gate and framing.
- The programme
- A live Decision Gate Cohort covering the decision gate process, decision quality and opportunity framing, ending with participants presenting a framed opportunity to a mock Decision Review Board.
- Who it’s for
- Project directors, sponsors, PMO and governance leads, and consultants in energy, mining and infrastructure: “anyone accountable for decisions that carry real financial and reputational risk.”
Credentials, writing & community
- The book
- Where Projects Are Won or Lost: A Practical Guide to Early Decisions, Framing, and Governance, with Austin Wilson, written as the handbook for her course, with a foreword from David Skinner.
- Education
- MSc in Economics and Engineering, Wrocław University of Economics and Business. Certificate IV in Training and Assessment (Training Services Australia).
- Certification
- Certified International Facilitator.
- Find her
- LinkedIn: /in/iwona-wilson · wilson.biz · academy.wilson.biz
The Host · Orion Matthews
Orion is an award-winning programmer, entrepreneur and technology executive who has spent the last decade in the engine room of major capital projects. He founded Queryon in Washington, D.C. in 2015 with a focus on data analytics and software for the construction industry, starting with bellwether client BP, whose project-controls solutions his team deployed globally, from the North Sea to Azerbaijan to Houston. Today he’s a recognized expert in PMO data analytics and project-controls reporting, serving billion-dollar portfolios for owners including BP, Santos, Balfour Beatty and Turner & Townsend, a regular speaker at major industry conferences on AI and analytics in capital projects, and the host of this show.
Why this pairing works
- Both saw the gap
- Iwona spent years writing audit reports on projects that were compliant and failing; Orion builds the reporting layer billion-dollar portfolios actually run on. Both ended up at the same question: the documents are all there, so why doesn’t leadership have confidence?
- Where they met
- At the AACE conference in Houston, where Orion picked up a signed copy of Iwona’s book, and read it in Hawaii before the recording.
- The AI question
- Orion works on the practical application of AI and analytics in capital projects; Iwona is watching what AI does to decision-making. They meet on the same caution: efficiency yes, but the consequences of a decision cannot be outsourced.
Beyond the PMO
- The builder’s arc
- Founded Introspect Software out of high school; built and sold Design-PT (acquired 2015). His software has run from McMurdo Station to aircraft carriers, with write-ups in Scientific American, CNN and Maxim, and a BP Helios Award.
The Quality Route In
Orion opens with the show’s standing frame, then hands Iwona the question every guest gets: how did you get here? Her answer is not the one you expect from someone who teaches billion-dollar governance. It starts in Poland, runs through a London brewery, and turns on one generous colleague.
“I got into the oil and gas industry and the capital projects through quality assurance, actually. I’m born and raised in Poland, and I did my master’s in engineering and economics, and my major at that time was quality assurance.”Iwona Wilson · ~1:15
The thesis that started it
Her master’s thesis was on implementing a food quality management system at Young’s Brewery in London, where she had worked. “At that time, quality assurance and ISO 9001 was a really big thing, and for me, it was a way for organizations to become more competitive, to boost their performance, build trust with customers, and really win a lot of work. So that’s how I used to see quality assurance.”
The door in
Working as a training coordinator for the Institute of Quality Assurance in London put her among trainers and experts. One of them (Mayank Rawal, “one of the nicest person I’ve ever met in the oil and gas industry”) saw her passion for quality management and pushed her to explore the industry. That led to a graduate place at MW Kellogg, now KBR. “That’s really where my career started.”
- The standing open: learning from people who work on projects over a billion dollars, “trying to tease out lessons and learnings from these big endeavors.”~0:05 · Orion sets the frame, then introduces Iwona’s twenty years across oil and gas, mining and capital projects in Australia, the UK and the US
- Poland, then a master’s in engineering and economics majoring in quality assurance.~1:20
- The brewery thesis, and the reason she left. “I really like drinking beer. However, I had this realization that working at the brewery and smelling hops every day wasn’t really something I loved.”~2:10
- Mayank Rawal, the Institute of Quality Assurance, and the graduate programme at MW Kellogg in London.~2:45
Decision Gate 101
Orion asks for a 101 “to help everyone, no matter where they came from, kind of understand what we’re talking about.” What follows is the most self-contained explanation of the stage gate process the show has run: origin, phase by phase, gate by gate, all the way through to the post-investment review. If you only listen to six minutes of this episode, listen to these.
“The idea is very simple. It’s really about moving an idea from the early thinking into the execution whilst reducing the uncertainty, the unknown that exists in a project. So it’s about taking an idea, initiative, or a project and breaking it into phases and gates.”Iwona Wilson · ~4:20
The phases, in her words
Assess: what is this opportunity, what’s the value proposition, the strategic fit, the major risks, and is there at least one way to realize it? Concept (or select): generate and analyse a whole range of creative alternatives, test the value drivers, land on one. Develop: take that concept further and prepare for execution. Execute: construct, procure, commission; the most visible part. New environment: hand over and evaluate whether you got what you said you would.
The four outcomes of a gate
At every gate, leadership pauses and asks one question: “Given all we know about the opportunity, do we still want to continue investing in this project?” The answer is one of four: proceed to the next phase, recycle (send the team back over the previous phase), hold if the timing isn’t right, or stop altogether. Proceed is also the moment funding and resources are released.
- Origin story: “the stage gate process, which I call the decision gate process, some people call it the phase gate process, was initially developed by Dr. Robert Cooper for product development, product innovation. And then later on it really moved into capital projects.”~3:40
- Most organizations run five phases and five gates; complexity and the nature of the opportunity can push that up or down.~4:45
- FID, defined plainly: “that’s when the organization announces they have a project, and they ask the question, ‘Are we truly ready to execute this project?’”~7:05
- The part most teams skip: the post-investment review, six to twelve months after the project moves into the new environment, evaluating the value actually delivered.~7:45
- What the process really is, in four registers: a governance tool, a decision-making system, a way of thinking, and ultimately a risk management tool.~8:15
“Stage gate is seen as a governance tool, and it is a governance tool. But for me, it’s really more a decision-making system, and also it’s a way of thinking. It’s a way to bring clarity around what we are dealing with. It’s a way to bring confidence for decision-makers and the project team so they know what they’re investing in. And it’s the way to connect stakeholders from across the organization and allow them to contribute.”Iwona Wilson · ~8:15
Compliance Isn’t Confidence
Orion pulls the two halves of her career together: what does ISO 9001 quality work have to do with decision gates? Iwona’s answer is the origin of everything else she teaches. As a QA engineer auditing EPC projects, she kept finding the same thing: projects that were fully compliant, and failing anyway. She could not explain why. So she went to the owner side to find out.
“Most projects were compliant. Most projects follow procedures. They use the right templates. They apply the right guidelines. The boxes get ticked. But despite that, many of those projects would experience challenges, especially during execution, and some of them would be even cancelled, and somehow I never really knew why.”Iwona Wilson · ~11:20
What passing a gate does not tell you
“Projects might pass gates, and might still carry political bias, or might still have hidden assumptions, and might still pass the gate with stakeholders being misaligned, if the focus is so much about passing the gate as opposed to improving decision-making during the gate.” Her audit reports, meanwhile, converged on the same findings every time: document control, communication, interfaces. All compliant. None of it moving the needle.
Why she crossed to the owner side
“It’s only when I got the opportunity to work for the owner organization and look at projects from the idea stage… that’s when I saw what’s possible and where value actually gets created, and where you cannot add any more value, where all you have to do is get things done as soon as possible.” Stage gate, taught properly, “can give you access, tools, language, and conversations” that help leaders make confident, informed decisions.
- The QA engineer’s job, described exactly: implement the project quality management system, then audit the project against contractual requirements, international standards and organizational policy.~10:40
- The moment the reports stopped meaning anything. “My audit reports after a while begin to be the same… I didn’t really feel like I’m making a big difference.”~12:40
- Orion brings in a mutual colleague, Akin Oni, and a title that has become shorthand in the space: The Operation Was Successful But The Patient Died. “You can follow all the procedures and still have high quality scores, but these projects were not actually being successful for the organizations.”~15:00
- Iwona extends the metaphor to contracting: “if the patient goes for a surgery and then dies at the end, it’s the family which will take the consequences. It’s not often the doctor that is following their own procedure and their own framework.”~16:30
- Who is actually accountable. “It’s the owner that has responsibility to set a project for success, because the owner focus is always long-term: how can we create with that project real value for the community, the environment, the organization itself.”~17:00
- The blunt corollary: “When I talk to construction companies, they are not that interested in stage gate process, because if there is a change, they just gonna ask the client to pay.”~17:45
“A good governance should improve the quality of your decisions. It’s not just about generating more documents. It’s not just about even document quality. It’s really about enabling leaders to make good decisions.”Iwona Wilson · ~14:40
From Deliverables to Decisions
If compliance isn’t confidence, what changes? Iwona is careful about attribution first: much of this comes from Robert Cooper on stage gate and from decision science, now taught as decision quality and promoted by the Society of Decision Professionals. Then she names the shift: most organizations structure projects around deliverables, templates and checklists, and the decision gate process asks them to structure around decisions instead. That single reframe changes what a team is asked to produce.
“The only reason we have phases is to prepare you for the next decision you need to make. The only reason you’re asked to produce deliverables is to enable some kind of decision.”Iwona Wilson · ~19:50
The waste this creates
“A lot of projects often get stuck, and they produce deliverables after deliverables without pausing to ask the question: what is the decision that we actually need to make? That’s gonna create a lot of unnecessary waste in terms of time and resources, and might lead to a lot of deliverables getting produced with no value for leadership to make the decision.”
What decision quality actually measures
“Decision quality is a standalone discipline that is measuring the quality of decisions you need to make based on the information you have available at the given time, regardless of the outcomes the decision is going to lead to.” The point that lands: a decision can be high quality and still turn out badly, and a lucky outcome does not make a decision good.
- Attribution, unprompted: stage gate from Dr. Robert Cooper; decision-making and opportunity framing from decision science, “which we really call now decision quality, promoted by organizations like the Society of Decision Professionals.”~18:30
- What leadership is actually there to understand at a gate: the decision, the options considered, where the information came from and whether it’s current, the value, the trade-offs, the logic behind the recommendation, and the commitment being asked of them. The six dimensions, introduced in passing.~21:00
- The failure mode named: “those organizations that still run the gate reviews heavily focused on activities and deliverables often lose the focus of what’s the intent of the gate review.”~22:00
- Orion asks the practitioner’s question: is the gate decision always proceed / recycle / hold / stop, or do secondary decisions get brought to a gate?~22:20
- The minimum-work principle. “What’s the minimum amount of work that we need to do to answer the main question at gate one? It’s not about doing all possible deliverables that we’ve ever done in our life.”~25:15
- The Fort Myers land analogy arrives (a block of land in Florida while you live in Oregon) and never leaves the episode.~25:45
“Ultimately, at every decision gate an organization is making two decisions. The first is: are we ready? Have we done what we said we would, assured the deliverables, answered the key decisions, tested the assumptions? And the second is: do we want to proceed? Which is more a business decision, given the market, given our strategy, given the current pricing, given what else is going on.”Iwona Wilson · ~28:15
Where Projects Are Won or Lost
Orion had planned to ask which decision matters most. The Florida analogy makes him rethink the question, and Iwona answers the version he didn’t quite ask. Everyone points at FID because that is the decision that goes public and releases the money. Her position is more precise than “the early stuff matters too”, and it is the sentence her book is named after.
“All decisions are equally important, but not all decisions have the same consequences. All decisions are very important, and they need to be answered. If they are not answered consciously, they’re answered unconsciously, through assumptions.”Iwona Wilson · ~32:15
Why the early gates are underestimated
“Many projects are already lost or won before that decision, and it’s really about how they treat those early decisions.” After assess and after concept is when leadership has to be crystal clear on what the opportunity is, what’s driving it, and what assumptions are being made about the present and the future. “This is where we’re often locking in our options, and that’s why those early decisions are often underestimated.”
What FID actually locks
“Once you pass the FID stage, it gets so much more expensive, plus it’s almost impossible to change. You are emotionally committed to your decision. The whole family and community already knows that you are now Floridian, so you’re politically connected to that decision and financially invested in that decision.” Three commitments, not one: emotional, political, financial.
- Why everyone believes FID is the most important gate: it’s when the project becomes public, when the most funding is released, and when the decision is treated as irreversible.~31:20
- The reframe (equal importance, unequal consequences) and the assumptions that fill the gap when a decision isn’t made consciously.~32:15
- Cheapness of change as the real argument: “when you’re gonna change your mind, change directions, new information is gonna become available, making changes at that stage is way cheaper than committing to change once you’re on the plane moving your family to Florida.”~33:40
- The payoff for doing early work well: a far more confident FID, with a clear story of the options considered, the target outcome and how the decision was made. “So it’s easy to create the story for the public: why do we think this is the right thing to do?”~34:30
- Orion’s counter-point, which she accepts: killing a project in assess is not wasted work; it tells the organization something worth knowing. “It helps me know where I’m gonna be spending my life and where to invest more energy.”~30:00
When Gate Reviews Become Theater
Two practical questions from Orion, aimed squarely at the executive listening. First: how do I set my team up with this mindset, when most engineers are deeply process-focused? Second, and sharper: how do I spot when a gate review looks healthy and isn’t? Iwona is explicit that she doesn’t run gate reviews (her work is upstream, framing opportunities and setting teams up for them), which is precisely why her warning signs are behavioural rather than procedural.
“How do we provide this grounding presentation? Is everything super polished? Do people ask questions? Do they challenge assumptions? Or do they just accept everything without any challenge?”Iwona Wilson · ~41:20
Start with your own current state
Before changing anything, get present with what you already have. “Get individuals together from different parts of the business, and run a little bit of a lessons learned workshop to understand what are some of the patterns running through your organization. What is currently happening? What are some of the processes that are already working for you? What aren’t working for you, and why?”
Then audit each element
Go element by element through the decision gate process: how gate review meetings run, how each phase starts, how projects are categorized and scaled, how inputs from different functions are invited, how teams are aligned on the work ahead, how uncertainty is reduced phase to phase, and whether assurance is actually producing insight that supports confident decisions.
- Know your role first: what the organization is for, what it expects from its projects, and whether you are the owner initiating projects or a party executing them. The answer changes everything downstream.~36:10
- The structure and agenda of the meeting itself “has a lot to do with how we establish a safe and also brave space for discussion.”~41:00
- Warning sign: at a second gate review, someone names a stakeholder who has never come up before. “Then you might know that probably stakeholder engagement have been done too late.”~42:10
- Warning sign: the meeting is mostly about how many documents are done and what their status is, rather than a conversation that improves the decision leadership is about to make.~42:30
- What a healthy team can do on demand at a gate: explain what the opportunity is about, name the major value driver, state the assumptions behind the selected option, and identify the biggest risk.~42:00
- The test for whether governance is working at all: “are leadership teams getting information that gives them clarity and confidence to approve those projects, so they can move forward, and kill those projects that are just badly framed projects?”~38:45
“There’s a lot that you can listen to and just watch, by listening to the quality of those conversations. And those warning signs might lead to a false confidence about the project.”Iwona Wilson · ~43:00
The Groan Zone
The longest and best stretch of the episode. Iwona explains why a traditional meeting is the wrong instrument for framing a complex opportunity, brings in Sam Kaner’s research on group decision-making to name the messy middle, and defends discomfort as a design feature rather than a facilitation failure. Then she does something unusual on a governance podcast: she describes how she and her husband run the same process at their own kitchen table, with Post-it notes.
“An opportunity framing workshop can be really messy, and can be painful, and they can be uncomfortable. But this is the cost of alignment.”Iwona Wilson · ~49:00
Why traditional meetings can’t do this
They are well designed to bring people together for a status update, not to make important decisions, explore a problem, or frame a big opportunity with a lot of moving parts. “If you bring a bunch of people together, people are usually not on their best behavior. They tend to protect their own interests, especially if you bring functional managers from different functions together.” And they self-censor: when the culture says “we’ve already covered this,” or “let’s keep it simple,” concerns stop being voiced.
What the facilitator is for
“You need someone with no vested interest in the outcome, that would purely be interested in helping the group go through the process”, carrying the team through the groan zone so they land with shared understanding of what they’re trying to achieve and what decision needs to be made. The neutrality is the qualification, not a nice-to-have.
- Sam Kaner’s three-part structure: diverge (invite opinions and questions); then somewhere in the middle, tension; then converge (narrow the thinking, plan the action, make the decision).~45:50
- The groan zone, and what leaders do when they hit it. “It gets messy. People feel the disagreement, discomfort… So what they do that moment, they say, ‘Well, let’s stop. Let’s schedule the next meeting for next week.’”~46:40
- The cost of avoiding it: “that’s why strategy meetings often take three months. If they could actually take one day or two days.”~47:20
- The claim that makes the discomfort worth it: “those teams that are able early on to go through those difficult conversations, the conflicts, those teams tend to execute faster with less surprises.”~47:50
- Orion connects it to forming, storming, norming, performing, and asks whether a conflict-avoidant team can even reach a good decision. Iwona’s answer: in the assess phase you don’t have a team yet, so the model applies less than you’d think.~49:20 → ~53:30
- The kitchen table method: “We take Post-it notes, me and my husband. We don’t sit opposite to each other. In fact, we don’t even look at each other, and we quietly write down what are some of the issues, questions, and concerns that we see in this coming opportunity.” Then they categorize, then they walk the wall. “We’re trying to get our thoughts out of our heads and make them visible on the wall.”~51:30
- Why framing is avoided in siloed organizations (different functions, different priorities, no willingness to come together) and why doing it consistently changes the culture rather than just the project.~53:50
- Challenger. Orion asks about the O-ring and the management override of the people on the ground. Iwona: “If people down on the ground are not invited to express their opinions, that is gonna impact decision-making. That is gonna often show up later on as a surprise that could have been prevented.”~57:45
- Her recommendation, stated flatly: “my recommendation is that every project has an opportunity framing workshop”, with operations, execution, regulatory, community, project controls, project management and HSE experience all in the room early.~58:20 → ~1:00:00
“If people don’t feel like they can contribute, they begin to disengage. They lose the trust in the process. They lose the trust in the governance, and then they often leave.”Iwona Wilson · ~55:40
Six Dimensions of Decision Quality
Orion admits he doesn’t know what the six dimensions are and asks whether he should have. Iwona walks the decision quality wheel one dimension at a time, and pre-empts the objection she always gets, which is that all six are obvious.
“A lot of people listen to those dimensions and they say, ‘Iwona, this is such common sense. Why are you even telling me this?’ Because it is so much common sense. And I often say that the biggest challenge is if the common sense isn’t applied early enough.”Iwona Wilson · ~1:02:20
You understand what you’re trying to achieve. You know what you know, and what you don’t.
You created and considered a wide range of options, not one option with variations.
You know where the information came from, and it is relevant and up to date.
You understand the value drivers, and what you are trading away for what.
You can demonstrate how the decision was reached. There is a process behind it.
The stakeholders who must act are committed. “If there’s no commitment, nothing happens.”
The rule · a decision is only as good as its weakest dimension
- What the wheel is for: it is a method you can use to measure alignment across the six dimensions before a major decision is made, or soon after, to check the quality of the one you made.~1:02:40
- The six, in her order: appropriate frame, creative alternatives, relevant information, values and trade-offs, sound logic, commitment to action.~1:02:45 → ~1:03:40
- The weakest-link rule. “So the quality of decision is as good as the weakest.”~1:03:50
- The two ways it breaks. “You might understand the trade-offs. You might understand where the information comes from. But if there’s no commitment, nothing happens.” And in reverse: “You might even have a commitment, but if you have poor quality information, if you’re making wrong assumptions, the quality of that decision will be really low, and the impact it will have will be damaging.”~1:04:00
- The commitment question, made concrete: “who are the key stakeholders that need to be involved? What amount of commitment is required to make that decision stick?”~1:05:50
- Where else it works: “you can actually get together with your team in any function, whatever decision you’re gonna make, and just go over those six and discuss it with your team before you make a decision or soon after.”~1:04:40
The Takeaway & the Billion-Dollar Math
Orion offers his own takeaway first: that decision-making can’t live only at the gates, and that the real prize is opportunity framing bubbling up organically through the rest of the organization. Then he asks Iwona for hers, and closes the loop by putting a number on the stakes.
“You need to aim to create some sort of language fluency across different functions, so we all speak from the same hymn sheet and we understand the decision gate process language. And you also need a framework for decision-making that people trust, that empowers individuals inside those teams to voice their opinion, and enables decision-makers to make good, confident decisions.”Iwona Wilson · ~1:08:10
Orion’s takeaway
“If you’re a really high performing organization, it seems to me that decision-making is not just at these gates. It’s actually something that needs to be inculcated into the entire organization somehow. And if you can actually find a way to work that same opportunity framing into the rest of your organization and your teams, and it’s organically bubbling up, that really is the prize.”
Iwona’s takeaway
Three things, in order: look honestly at the decision gate mindset your organization actually has; build language fluency across functions so everyone means the same thing by the same words; and give people a decision-making framework they trust enough to speak up inside.
“For a billion-dollar project… if you do ten billion-dollar projects, you will expect five of them to overrun, and your average of those overruns is gonna be about $500 million. So when you budget a billion-dollar project, you budget an average overrun of $500 million. That’s how bad our decision making is in this space, but it’s also just the opportunity that’s on the table if you have good decision making.”
Orion cites these numbers from memory on air. He says as much: “I think I looked these numbers up a little while ago.” Treat them as directional rather than as a sourced statistic. The order of magnitude is consistent with the published megaproject literature on cost overrun frequency and severity, but the specific 50% / $500M pairing is not attributed to a study in the conversation and should not be quoted as one.
- Iwona’s takeaway: mindset, language fluency, and a framework people trust.~1:07:40
- Orion’s framing of the gravity: “something we probably should have told people in the beginning.”~1:08:50
- The upside argument: getting decision-making right “could make a huge difference between an organization surviving or not, in many ways.”~1:09:45
The Capability Gap
This is the exchange the episode takes its name from. Orion puts the question that had been on his list all along: everybody in major capital projects says they have a stage gate process, so why do we keep seeing billion-dollar surprises? Iwona’s answer is the sentence the whole conversation has been building toward, and then she does something better than restate it: she describes the two opposite ways process maturity goes wrong.
“Companies do have stage gate process in place, but they still experience project overruns, cancellation, or they create projects with not enough value based on what they wanted. And that is happening because having a process in place is not the same as having capabilities. That’s the biggest misconception in this industry.”Iwona Wilson · ~1:33:10
What organizations have
“Some phases, some gates, maybe some templates, maybe approval lists, maybe even mandatory checklists for the gate review.”
What is missing
“Very few organizations actually teach how to think through uncertainty, how to frame opportunities, how to create alignment around key stakeholders, how to identify, name, and challenge assumptions, how to make quality decisions, how to understand when a project is heading in the wrong direction.”
- When companies actually call. “Many companies ask about stage gate process usually after something major happens, after a major overrun, or some big public issue, or investor pressure or community pressure, or change of leadership, or some operational underperformance that happens over a long time.”~1:34:40
- The distinction, named. “That’s usually when they begin to see there is a difference between having an approval system and having a decision-making system.”~1:35:10
- The knowledge gap between the mature majors and the fast-growing companies that have never developed a project: the ones who “tend to run into execution, skip stakeholders alignment, skip option analysis, and are often not clear around the real value of what they’re trying to achieve.”~1:35:40
- Orion’s good question: can you backslide on capability while keeping the process? Which opens the second failure mode.~1:36:40
- The over-developed end. “A lot of them, with well-defined stage gate process, develop so much in the process that the process gets very bureaucratic”: massive document production, impossible gate requirements, excessive approvals, lengthy decision cycles. “And then the conversation on the project team, rather than how can we improve decision quality, is all about how can we pass the gate.”~1:37:30
- What that does to people: “people begin to lose trust in the process, they detach, and they produce documents to ensure compliance as opposed to create clarity.”~1:38:30
- The best-kept secret. Opportunity framing “is usually only known by the top companies in oil and gas, Chevron, Shell, Woodside”: companies that have matured their stage gate for three or four decades and use framing “not just as a best practice, but as a mandatory approach to start the initiatives.”~1:38:50
- Outside those organizations: “teams rely on individual experiences. They assume alignment. They don’t test the alignment. They call assumptions givens. They don’t challenge them.”~1:39:50
- Why stage gate emerges at all: “most organizations really started stage gate process because they started looking at more than one project. And when you have more than one project, you really need to be cautious where you’re going to invest.”~1:42:20
- Orion’s aside on organizations that wait until they’re big enough (“the 10,000 employee organization definitely started the stage gating before they reached that size”) and Iwona’s reply for the smaller companies: leverage the principles now rather than waiting.~1:41:00 → ~1:43:00
“Move from developing faster to developing smarter. That’s really what I think: that’s where the opportunity is.”Iwona Wilson · ~1:43:00
“Some people would even say that your success is only one decision away.” ~1:44
The Big Ideas
Three ideas carry the episode. Sketched here the way a framing facilitator would whiteboard them at the front of a room, plus a fourth, the decision quality chain, drawn in chapter 08 where it belongs.
Two organizations can hold identical process documentation and be doing completely different things with it. What separates them is not the framework: it is the set of capabilities that make the framework mean something. That set is what almost nobody buys, teaches or measures.
An approval system
- Phases and gates on a wall chart
- Templates and guidelines
- Approval lists and mandatory checklists
- Deliverable status as the gate conversation
- The question is: can we pass?
A decision-making system
- Thinking through uncertainty
- Framing opportunities before they’re projects
- Aligning stakeholders across functions
- Naming and challenging assumptions
- The question is: is this a good decision?
The organization’s attention follows the money, which means it arrives exactly when changing your mind has become most expensive. The leverage sits in the quadrant nobody is watching.
Cheapest to change · lowest attention. What is the opportunity, what’s the value proposition, is there at least one way to realize it? Highest leverage in the whole lifecycle.
Expensive to change · attention arriving. Concept locked, estimate built on framing assumptions, the story being written for the public.
Still cheap to change · still private. Options generated and analysed, value drivers tested, one alternative chosen. Options quietly get locked here.
Near-irreversible · maximum attention. Emotionally, politically and financially committed. “The contractor just gonna send you an invoice.”
Diversity in the room produces tension; tension is what shared understanding is made of. The only real choice is whether you pass through it in two days with a neutral facilitator, or over three months of rescheduled meetings.
From the Bonus Episode
The companion episode turns from governance to the people who will inherit it. Orion asks what advice Iwona would give a student watching who wants into this space, and the answer has nothing to do with software or certifications. Quotations below are her own words, lightly condensed, with approximate positions in the full recording; the split between the main and bonus cuts is Orion’s edit, so a line’s exact position in the published bonus will differ.
“Seek opportunities where you can polish your critical thinking skills. This is what I love the most about opportunity framing, where people see there is a distinction between a given and an assumption. When people see that actually a lot of the stuff can be negotiated.”Iwona Wilson · bonus material, recording ~1:11
Why critical thinking, and why now
“If I think about the next generation of leaders and what would be really useful for them, given the challenges that we have in most countries, as well as the rise of AI, I would say seek opportunities where you can polish your critical thinking skills.”
Bonus material · recording ~1:10:50
Where to go and find it
“I know that University of Houston, for example, they have their own chapter, Society of Decision Professionals, and they’re always open to bring new people on board. They collaborate with the industry, with large organizations, with myself, bringing different individuals who teach students some of those decision-making tools that they can apply in their life.”
Bonus material · recording ~1:12:10
The AI line she won’t cross
“If we let AI make decisions for us, there are still consequences that will have to be absorbed: the project, the organization, the teams will be impacted. And the AI is not gonna pay for whatever’s gonna come out of our decisions.”
Bonus material · recording ~1:16:20
Where AI does earn its place
“AI can definitely speed up a lot of the tasks that we do. It can help with brainstorming, by helping to categorize and organize our thoughts. So I can see ways even inside the workshop where we can save some time by adding an AI component… but making sure that technology is not ahead of the humans.”
Bonus material · recording ~1:18:00
What framing gives a young engineer
“There’s nothing more empowering for young individuals than giving them tools so they can make their own decisions confidently… and really be the one who knows how to ask important questions before those decisions are made.”
Bonus material · recording ~1:12:40
The unexpected turn
“I go a little bit against the foundation in decision analysis that everything needs to be logical, because I do think that you can also attract good luck for your project. You can attract the right stakeholders and contractors… Create that excitement for what it is that you’re trying to achieve. Be very clear on intention. Allow people to contribute. But at the same time, detach: if it’s not the right time, don’t get upset about it.”
Bonus material · recording ~1:22:40 and ~1:24:40
Quote Bank
The best on-the-record lines, gathered in one filterable place. “Highlight” marks the lines most worth scrubbing back for. Quotes are lightly condensed with meaning untouched; timestamps are approximate positions in the full recording.
The Quality Route In 0:00–3:30
- “I got into the oil and gas industry and the capital projects through quality assurance, actually.”
- “At that time, quality assurance and ISO 9001 was a really big thing, and for me it was a way for organizations to become more competitive, to boost their performance, build trust with customers, and really win a lot of work.”
- “I really like drinking beer. However, I had this realization that working at the brewery and smelling hops every day wasn’t really something I loved.”
Decision Gate 101 3:30–9:15
- Highlight“The idea is very simple. It’s really about moving an idea from the early thinking into the execution whilst reducing the uncertainty, the unknown that exists in a project.”
- “During the gate the leadership would pause and would ask the question: ‘Given all we know about the opportunity, do we still want to continue investing in this project?’”
- “The final investment decision, that’s when the organization announces they have a project, and they ask the question, ‘Are we truly ready to execute this project?’”
- Highlight“Stage gate is seen as a governance tool, and it is a governance tool. But for me, it’s really more a decision-making system, and also it’s a way of thinking.”
- “That was like an entire course. If you have someone starting on a major project, we could just clip that and give it to them.”
Compliance Isn’t Confidence 9:15–18:00
- Highlight“Most projects were compliant. They follow procedures. They use the right templates. The boxes get ticked. But many of those projects would experience challenges, and some of them would be even cancelled, and somehow I never really knew why.”
- Highlight“Projects might pass gates, and might still carry political bias, or hidden assumptions, and might still pass the gate with stakeholders being misaligned, if the focus is so much about passing the gate as opposed to improving decision-making during the gate.”
- “My audit reports after a while begin to be the same. They would report on the same issues around document control, communication, interfaces… I didn’t really feel like I’m making a big difference.”
- Highlight“A good governance should improve the quality of your decisions. It’s not just about generating more documents.”
- “It’s the owner that has responsibility to set a project for success, because the owner focus is always long-term.”
- “When I talk to construction companies, they are not that interested in stage gate process, because if there is a change, they just gonna ask the client to pay.”
From Deliverables to Decisions 18:00–29:00
- Highlight“The only reason we have phases is to prepare you for the next decision you need to make. The only reason you’re asked to produce deliverables is to enable some kind of decision.”
- “A lot of projects often get stuck, and they produce deliverables after deliverables without pausing to ask: what is the decision that we actually need to make?”
- “Decision quality is a standalone discipline that is measuring the quality of decisions based on the information you have available at the given time, regardless of the outcomes the decision is going to lead to.”
- “What’s the minimum amount of work that we need to do to answer the main question at gate one? It’s not about doing all possible deliverables that we’ve ever done in our life.”
- Highlight“At every decision gate an organization is making two decisions. Are we ready to proceed, and do we want to proceed?”
Where Projects Are Won or Lost 29:00–35:00
- Highlight“All decisions are equally important, but not all decisions have the same consequences.”
- Highlight“If they are not answered consciously, they’re answered unconsciously, through assumptions.”
- “Many projects are already lost or won before that decision, and it’s really about how they treat those early decisions.”
- “Once you pass the FID stage, it gets so much more expensive, plus it’s almost impossible to change. You are emotionally committed to your decision.”
- “Making changes at that stage is way cheaper than committing to change once you’re on the plane moving your family to Florida.”
When Gate Reviews Become Theater 35:00–44:00
- Highlight“Is everything super polished? Do people ask questions? Do they challenge assumptions? Or do they just accept everything without any challenge?”
- “If all of a sudden someone mentions a stakeholder that hasn’t been mentioned earlier on, then you might know that probably stakeholder engagement have been done too late.”
- “Run a little bit of a lessons learned workshop to understand what are some of the patterns running through your organization.”
- “Are leadership teams getting information that gives them clarity and confidence to approve those projects, so they can move forward, and kill those projects that are just badly framed projects?”
- “Those warning signs might lead to a false confidence about the project.”
The Groan Zone 44:00–1:01:00
- “If you bring a bunch of people together, people are usually not on their best behavior. They tend to protect their own interests.”
- “They often self-censor themselves… because the culture of the organization is, ‘Let’s keep it going. Let’s move on.’”
- Highlight“He calls it the groan zone. It gets messy. People feel the disagreement, discomfort. And a lot of leaders don’t like sitting in that place, so they say, ‘Well, let’s stop. Let’s schedule the next meeting for next week.’”
- “And that’s why strategy meetings often take three months. If they could actually take one day or two days.”
- Highlight“Those teams that are able early on to go through those difficult conversations, the conflicts, those teams tend to execute faster with less surprises.”
- Highlight“An opportunity framing workshop can be really messy, and can be painful, and they can be uncomfortable. But this is the cost of alignment.”
- “We take Post-it notes, me and my husband. We don’t sit opposite to each other. In fact, we don’t even look at each other, and we quietly write down what are some of the issues, questions, and concerns.”
- “We’re trying to get our thoughts out of our heads and make them visible on the wall.”
- “If people don’t feel like they can contribute, they begin to disengage. They lose the trust in the process, and then they often leave.”
- Highlight“If people down on the ground are not invited to express their opinions, that is gonna impact decision-making. That is gonna often show up later on as a surprise that could have been prevented.”
Six Dimensions of Decision Quality 1:01:00–1:06:00
- “A lot of people listen to those dimensions and they say, ‘Iwona, this is such common sense.’ … The biggest challenge is if the common sense isn’t applied early enough.”
- Highlight“So the quality of decision is as good as the weakest.”
- Highlight“You might understand the trade-offs. You might understand where the information comes from. But if there’s no commitment, nothing happens.”
- “Who are the key stakeholders that need to be involved? What amount of commitment is required to make that decision stick?”
The Takeaway & the Billion-Dollar Math 1:06:00–1:10:00
- Highlight“You need to aim to create some sort of language fluency across different functions, so we all speak from the same hymn sheet, and a framework for decision-making that people trust.”
- “Decision-making is not just at these gates. It’s actually something that needs to be inculcated into the entire organization somehow… that really is the prize.”
- “When you budget a billion-dollar project, you budget an average overrun of $500 million.”
The Capability Gap 1:32:00–1:44:00
- Highlight“Having a process in place is not the same of us having capabilities. So that’s the biggest misconception in this industry.”
- Highlight“Very few organizations actually teach how to think through uncertainty, how to frame opportunities, how to create alignment around key stakeholders, how to identify, name, and challenge assumptions.”
- “Many companies ask about stage gate process usually after something major happens, after a major overrun, or some big public issue, or investor pressure or community pressure, or change of leadership.”
- Highlight“That’s usually when they begin to see there is a difference between having an approval system and having a decision-making system.”
- “The conversation on the project team, rather than how can we improve decision quality, it’s all about how can we pass the gate.”
- “People begin to lose trust in the process, they detach, and they produce documents to ensure compliance as opposed to create clarity.”
- “Opportunity framing is still one of the best-kept secrets in the oil and gas industry.”
- Highlight“They assume alignment. They don’t test the alignment. They call assumptions givens. They don’t challenge them.”
- Highlight“Move from developing faster to developing smarter. That’s where the opportunity is.”
- Highlight“Some people would even say that your success is only one decision away.”
From the Bonus Episode “The One Skill Every Future Project Leader Needs”
- Highlight“Seek opportunities where you can polish your critical thinking skills.”
- “This is what I love the most about opportunity framing, where people see there is a distinction between a given and an assumption.”
- Highlight“If we let AI make decisions for us, there are still consequences that will have to be absorbed. And the AI is not gonna pay for whatever’s gonna come out of our decisions.”
- “Making sure that technology is not ahead of the humans.”
- “There’s nothing more empowering for young individuals than giving them tools so they can make their own decisions confidently.”
- “Create that excitement for what it is that you’re trying to achieve. Be very clear on intention… But at the same time, detach. If it’s not the right time, don’t get upset about it.”
Bookshelf & Links
Everything recommended in the episode, plus where to find the people and the show. Also collected on The Major Project Bookshelf.
Iwona’s bookshelf
- Her book
- Where Projects Are Won or Lost: A Practical Guide to Early Decisions, Framing, and Governance · Iwona Wilson and Austin Wilson. “This is a very short book, and it was intentionally designed as a handbook for my course participants… If someone just wants a quick short version, this is a really good resource.” A second edition with case studies is in planning.
- The foundation
- Introduction to Decision Analysis · David C. Skinner, founder of the Society of Decision Professionals, who wrote the foreword to Iwona’s book. “It gives you a real solid foundation to decision science, including opportunity framing, probabilities, how do we assess uncertainties. Those of you who are really into analysis and statistics are gonna have a ball.”
- The body of knowledge
- Society of Decision Professionals · “If someone is really serious about decision quality, the whole science behind decision-making, I recommend joining the Society of Decision Professionals.” Non-profit with chapters worldwide, including Houston and a University of Houston student chapter. She also points to the recommended reading list on their site.
- Referenced on the show
- Sam Kaner’s research on collaborative group decision-making, the source of the “groan zone.” Iwona cites the research rather than a specific title; his standard work is Facilitator’s Guide to Participatory Decision-Making. Dr. Robert Cooper is credited as the originator of the stage gate process for product development.
- Raised by Orion
- The Challenger Sale · Matthew Dixon and Brent Adamson, on changing a buyer’s mindset as the most powerful kind of sale. Orion also mentions Akin Oni’s The Operation Was Successful But The Patient Died, well known in the project-controls community; we could not verify a current product page to link.
- Work with her
- wilson.biz · consulting, facilitation and the 90-second project diagnostic · academy.wilson.biz · the Decision Gate Cohort.
- Where to catch her
- Mentioned on the show: a two-hour masterclass at the Global Project Management Forum in Riyadh in September, and the PMI Houston conference in August.
The episode
- Listen
- Episode page (Podbean) · Apple Podcasts · Spotify
- The guest
- Iwona Wilson on LinkedIn · Wilson Biz Consulting
- The host
- Orion Matthews on LinkedIn · Queryon
- The show
- themajorprojectpodcast.com · new conversations from the people building projects over US$1 billion. Also on Amazon Music and iHeartRadio.
Banner photographs are open-licensed historic images of oil, gas and process plants, used illustratively to evoke the sector: they are not the projects discussed in this episode. Left: South Brisbane Gas Company, December 1957, Queensland State Archives · Public Domain Mark 1.0. Centre: Early process for liquifying bitumen, Fort McMurray, Alberta, c.1935, Provincial Archives of Alberta (Robert C. Fitzsimmons fonds, ref. A.3383) · No known copyright restrictions. Right: Sheep near the Moonie oil rig, c.1968 (Australia’s first commercial oilfield) · Queensland State Archives · Public Domain Mark 1.0. Headshots are the guest’s and host’s own professional portraits.