The hidden reason billion-dollar projects overrun even with a stage gate

Iwona Wilson, co-founder and CEO of Wilson Biz Consulting, and the person who taught decision gate process at one of Australia’s largest energy producers for eleven years, on the question most organizations don’t ask until after the overrun: are we making good decisions, or just passing gates?

Iwona Wilson Iwona WilsonGuest · Co-Founder & CEO, Wilson Biz Consulting
Orion Matthews Orion MatthewsHost · Founder, Queryon
Released Jun 15, 2026 Episode 017 · 1h 07m + Bonus · 34 min Decision gates · $1B+ capital projects
Historic oil, gas & process plants, 1935–1976 · illustrative, not the projects discussed · full credits
Jump in Watch on YouTube Listen · Apple Podcasts Spotify
More ways to listen
Bonus episode · 34 min Watch bonus episode Full transcript
Share: LinkedIn X
The Conversation

Episode Overview

Every major capital project team will tell you they have a stage gate process. Iwona Wilson’s argument is that having the process and having the capability to use it are two completely different things, and that the distance between them is where billion-dollar surprises come from. She spent the first part of her career auditing projects for compliance and watching compliant projects fail anyway; then eleven years on the owner side at one of Australia’s largest energy producers, designing and teaching the decision gate process and facilitating the opportunity framing workshops that happen before anyone calls it a project. In this conversation she gives a complete 101 on phases and gates, explains why the final investment decision is the wrong place to look for leverage, walks through the six dimensions of decision quality and the one that always fails, and makes the case that the messy, uncomfortable middle of a framing workshop is not a process failure but the price of alignment.

1h 41m
Published across the main episode (1h 07m) and the bonus (34 min)
16,100
Words on the record across the full recorded conversation
73 / 27
Talk split: Iwona / Orion, by words spoken
6
Dimensions of decision quality: your decision is only as good as the weakest one
The thesis

A process is not a capability

Phases, gates, templates and mandatory checklists are an approval system. Framing opportunities, naming and challenging assumptions, aligning functions and measuring decision quality are a decision-making system. Most organizations have built the first and assume they bought the second.

The guest

Quality auditor turned framing facilitator

Iwona came into capital projects through ISO 9001 quality assurance at MW Kellogg and Foster Wheeler, then spent eleven years at Woodside Energy in Perth as an opportunity framing facilitator, trainer and project advisor. Since 2021 she has run Wilson Biz Consulting out of Houston.

The bonus

The one skill for the next generation

A 34-minute companion episode on critical thinking as the skill that survives AI, where students should go to build it, and why Iwona thinks belief and detachment belong in the same conversation as decision analysis.

About this brief

Every quotation here is Iwona Wilson’s or Orion Matthews’ own on-the-record words from the recorded conversation, lightly condensed for readability with meaning untouched. Timestamps are approximate and refer to positions in the full recording, which was published as an edited main episode plus a bonus episode, so a quote’s clock position in the brief will not always match the published cut. Career facts, dates, employers and locations come only from Iwona’s public LinkedIn profile and what she said on air; she speaks in a personal capacity. Chapter titles and the chapter map are editorial. Where an on-air figure was cited from memory, it is labelled as directional rather than repeated as fact. Banner photographs are open-licensed historic images of oil, gas and process plants, used illustratively: they are not the projects discussed; full credits are in Bookshelf & Links.

As Recorded

Episode Timeline

The conversation as it actually unfolded: ten chapters across roughly 81 minutes of on-the-record material, mapped against the show’s four-act structure. Click any block to jump to its chapter. The final block sits apart: it is the exchange the episode takes its title from, recorded after the formal wrap and carried into the published episode.

0:003.5 min01

The Quality Route In

The welcome, and how a master’s thesis on brewery quality management became a career in billion-dollar capital projects.

3:306 min02

Decision Gate 101

Phases and gates end to end: assess, concept, develop, FID, execute, and the post-investment review nobody talks about.

9:159 min03

Compliance Isn’t Confidence

Years of audit reports on compliant projects that failed anyway, and the move to the owner side to find out why.

18:0011 min04

From Deliverables to Decisions

The mindset shift that changes what a team is asked to produce, the minimum-work question, and the two decisions at every gate.

29:006 min05

Where Projects Are Won or Lost

Why FID is the wrong place to look for leverage, told through a family deciding whether to move to Florida.

35:009 min06

When Gate Reviews Become Theater

The warning signs an executive can watch for from the back of the room, and what a lessons-learned sweep of your own process turns up.

44:0017 min07

The Groan Zone

Why traditional meetings can’t frame a complex opportunity, the neutral facilitator’s job, Post-it notes at the kitchen table, and Challenger.

1:01:005 min08

Six Dimensions of Decision Quality

The decision quality wheel, walked through one dimension at a time, and the weakest-link rule that governs all six.

1:06:004 min09

The Takeaway & the Billion-Dollar Math

Language fluency as the goal, and Orion puts a number on what bad decision-making costs a billion-dollar portfolio.

1:32:0011 min10

The Capability Gap

The exchange the episode is named for: everyone has a stage gate, so why the billion-dollar surprises? Plus the two failure modes at either end of process maturity.

Who carried the mic

Iwona Wilson · ~11,850 words across 83 turns (guest) Orion Matthews · ~4,290 words across 83 turns (host)

Perfectly even turn-taking, heavily guest-weighted in volume: 166 speaker turns, and Iwona’s longest single answer runs over 800 words. Measured across the full recorded conversation.

The Guest

The Guest · Iwona Wilson

Iwona Wilson
Iwona Wilson
Co-Founder & CEO, Wilson Biz Consulting · Author, Where Projects Are Won or Lost · Certified International Facilitator
Houston, Texas, United States
Decision Gate ProcessOpportunity FramingDecision QualityFront-End LoadingProject Governance

Iwona Wilson came into capital projects sideways: through quality. Born and raised in Poland, she took a master’s in economics and engineering at Wrocław University of Economics and Business with a major in quality assurance, and wrote her thesis on installing a food quality management system in a London brewery. A chance encounter at the Institute of Quality Assurance in London led to a graduate place at MW Kellogg (now KBR), then quality assurance engineering at Foster Wheeler on FEED and EPCm work for ExxonMobil, Statoil and Sasol across the UK and Norway. In 2010 she crossed to the owner side, spending eleven years at Woodside Energy in Perth as an opportunity framing facilitator, trainer and project advisor, designing and teaching the decision gate process, and becoming the business’s subject-matter expert on professional facilitation. Since 2021 she has co-founded and run Wilson Biz Consulting from Houston, where she facilitates framing workshops for owner teams, implements decision gate process, and teaches a live Decision Gate Cohort.

“Capital projects are won or lost before they even begin. Most projects don’t fail because teams can’t execute. They fail because the problem was never clearly defined, stakeholders aligned too late, risks surfaced after commitment, and decisions rested on untested assumptions. I was always the person in the room asking the uncomfortable questions early, the thinker among the doers.”Iwona Wilson · from her public LinkedIn profile
17+
Years across oil & gas, mining and capital projects
11
Years at Woodside Energy teaching and facilitating decision gate
3
Continents worked: Europe, Australia, North America
5
Years as co-founder and CEO of Wilson Biz Consulting

Career journey

Quality assurance · contractor side
Owner side · opportunity framing & decision gate at Woodside
Founder · Wilson Biz Consulting
London
EPC · UK/Norway
Perth, Western Australia · LNG
Houston, Texas · consulting
01The Charter Quality InstituteTraining Coordinator2004–2006 · London
02MW Kellogg (now KBR)Quality Specialist2007–2008 · Kårstø Expansion Project, StatoilHydro
03Foster WheelerSenior Quality Assurance Engineer2008–2010 · Reading, UK & Norway
04Woodside EnergyOpportunity Framing Facilitator, Trainer & Project Advisor2010–2021 · Perth, WA
05PMI Coastal Bend ChapterChapter President2022–2023 · Corpus Christi, TX
06Wilson Biz ConsultingCo-Founder & CEO2021–present · Houston, TX

At Wilson Biz Consulting

The remit
Helping owners and leadership teams on complex projects strengthen early-stage framing, alignment and governance, through facilitated workshops and summits, project governance implementation, and training in front-end loading, stage gate and framing.
The programme
A live Decision Gate Cohort covering the decision gate process, decision quality and opportunity framing, ending with participants presenting a framed opportunity to a mock Decision Review Board.
Who it’s for
Project directors, sponsors, PMO and governance leads, and consultants in energy, mining and infrastructure: “anyone accountable for decisions that carry real financial and reputational risk.”

Credentials, writing & community

The book
Where Projects Are Won or Lost: A Practical Guide to Early Decisions, Framing, and Governance, with Austin Wilson, written as the handbook for her course, with a foreword from David Skinner.
Education
MSc in Economics and Engineering, Wrocław University of Economics and Business. Certificate IV in Training and Assessment (Training Services Australia).
Certification
Certified International Facilitator.
The Host

The Host · Orion Matthews

Orion Matthews
Orion Matthews
Founder, Queryon · Host, The Major Project Podcast · PMO data & analytics
Eugene, Oregon, United States
Project Controls ReportingPMO Data AnalyticsCapital PortfoliosAI in ProjectsPower BI

Orion is an award-winning programmer, entrepreneur and technology executive who has spent the last decade in the engine room of major capital projects. He founded Queryon in Washington, D.C. in 2015 with a focus on data analytics and software for the construction industry, starting with bellwether client BP, whose project-controls solutions his team deployed globally, from the North Sea to Azerbaijan to Houston. Today he’s a recognized expert in PMO data analytics and project-controls reporting, serving billion-dollar portfolios for owners including BP, Santos, Balfour Beatty and Turner & Townsend, a regular speaker at major industry conferences on AI and analytics in capital projects, and the host of this show.

Why this pairing works

Both saw the gap
Iwona spent years writing audit reports on projects that were compliant and failing; Orion builds the reporting layer billion-dollar portfolios actually run on. Both ended up at the same question: the documents are all there, so why doesn’t leadership have confidence?
Where they met
At the AACE conference in Houston, where Orion picked up a signed copy of Iwona’s book, and read it in Hawaii before the recording.
The AI question
Orion works on the practical application of AI and analytics in capital projects; Iwona is watching what AI does to decision-making. They meet on the same caution: efficiency yes, but the consequences of a decision cannot be outsourced.

Beyond the PMO

The builder’s arc
Founded Introspect Software out of high school; built and sold Design-PT (acquired 2015). His software has run from McMurdo Station to aircraft carriers, with write-ups in Scientific American, CNN and Maxim, and a BP Helios Award.
Chapter 01 · Act I · 0:00

The Quality Route In

Orion opens with the show’s standing frame, then hands Iwona the question every guest gets: how did you get here? Her answer is not the one you expect from someone who teaches billion-dollar governance. It starts in Poland, runs through a London brewery, and turns on one generous colleague.

“I got into the oil and gas industry and the capital projects through quality assurance, actually. I’m born and raised in Poland, and I did my master’s in engineering and economics, and my major at that time was quality assurance.”Iwona Wilson · ~1:15

The thesis that started it

Her master’s thesis was on implementing a food quality management system at Young’s Brewery in London, where she had worked. “At that time, quality assurance and ISO 9001 was a really big thing, and for me, it was a way for organizations to become more competitive, to boost their performance, build trust with customers, and really win a lot of work. So that’s how I used to see quality assurance.”

The door in

Working as a training coordinator for the Institute of Quality Assurance in London put her among trainers and experts. One of them (Mayank Rawal, “one of the nicest person I’ve ever met in the oil and gas industry”) saw her passion for quality management and pushed her to explore the industry. That led to a graduate place at MW Kellogg, now KBR. “That’s really where my career started.”

Key moments
  1. The standing open: learning from people who work on projects over a billion dollars, “trying to tease out lessons and learnings from these big endeavors.”~0:05 · Orion sets the frame, then introduces Iwona’s twenty years across oil and gas, mining and capital projects in Australia, the UK and the US
  2. Poland, then a master’s in engineering and economics majoring in quality assurance.~1:20
  3. The brewery thesis, and the reason she left. “I really like drinking beer. However, I had this realization that working at the brewery and smelling hops every day wasn’t really something I loved.”~2:10
  4. Mayank Rawal, the Institute of Quality Assurance, and the graduate programme at MW Kellogg in London.~2:45
Worth pausing on She names the person who opened the door, unprompted and by name. It is a small thing, and it recurs later: the through-line of this whole episode is that the useful knowledge in capital projects moves person to person, in rooms where people feel invited to speak.
Chapter 02 · Act II · 3:30

Decision Gate 101

Orion asks for a 101 “to help everyone, no matter where they came from, kind of understand what we’re talking about.” What follows is the most self-contained explanation of the stage gate process the show has run: origin, phase by phase, gate by gate, all the way through to the post-investment review. If you only listen to six minutes of this episode, listen to these.

“The idea is very simple. It’s really about moving an idea from the early thinking into the execution whilst reducing the uncertainty, the unknown that exists in a project. So it’s about taking an idea, initiative, or a project and breaking it into phases and gates.”Iwona Wilson · ~4:20

The phases, in her words

Assess: what is this opportunity, what’s the value proposition, the strategic fit, the major risks, and is there at least one way to realize it? Concept (or select): generate and analyse a whole range of creative alternatives, test the value drivers, land on one. Develop: take that concept further and prepare for execution. Execute: construct, procure, commission; the most visible part. New environment: hand over and evaluate whether you got what you said you would.

The four outcomes of a gate

At every gate, leadership pauses and asks one question: “Given all we know about the opportunity, do we still want to continue investing in this project?” The answer is one of four: proceed to the next phase, recycle (send the team back over the previous phase), hold if the timing isn’t right, or stop altogether. Proceed is also the moment funding and resources are released.

Key moments
  1. Origin story: “the stage gate process, which I call the decision gate process, some people call it the phase gate process, was initially developed by Dr. Robert Cooper for product development, product innovation. And then later on it really moved into capital projects.”~3:40
  2. Most organizations run five phases and five gates; complexity and the nature of the opportunity can push that up or down.~4:45
  3. FID, defined plainly: “that’s when the organization announces they have a project, and they ask the question, ‘Are we truly ready to execute this project?’”~7:05
  4. The part most teams skip: the post-investment review, six to twelve months after the project moves into the new environment, evaluating the value actually delivered.~7:45
  5. What the process really is, in four registers: a governance tool, a decision-making system, a way of thinking, and ultimately a risk management tool.~8:15
“Stage gate is seen as a governance tool, and it is a governance tool. But for me, it’s really more a decision-making system, and also it’s a way of thinking. It’s a way to bring clarity around what we are dealing with. It’s a way to bring confidence for decision-makers and the project team so they know what they’re investing in. And it’s the way to connect stakeholders from across the organization and allow them to contribute.”Iwona Wilson · ~8:15
Don’t miss Orion’s reaction at ~9:00 is the best endorsement of a segment this show has produced: “That was like an entire course. If you have someone starting on a major project, we could just clip that and give it to them and be like, ‘We’re in appraise right now.’” If you onboard people onto capital projects, this is the clip.
Chapter 03 · Act II · 9:15

Compliance Isn’t Confidence

Orion pulls the two halves of her career together: what does ISO 9001 quality work have to do with decision gates? Iwona’s answer is the origin of everything else she teaches. As a QA engineer auditing EPC projects, she kept finding the same thing: projects that were fully compliant, and failing anyway. She could not explain why. So she went to the owner side to find out.

“Most projects were compliant. Most projects follow procedures. They use the right templates. They apply the right guidelines. The boxes get ticked. But despite that, many of those projects would experience challenges, especially during execution, and some of them would be even cancelled, and somehow I never really knew why.”Iwona Wilson · ~11:20

What passing a gate does not tell you

“Projects might pass gates, and might still carry political bias, or might still have hidden assumptions, and might still pass the gate with stakeholders being misaligned, if the focus is so much about passing the gate as opposed to improving decision-making during the gate.” Her audit reports, meanwhile, converged on the same findings every time: document control, communication, interfaces. All compliant. None of it moving the needle.

Why she crossed to the owner side

“It’s only when I got the opportunity to work for the owner organization and look at projects from the idea stage… that’s when I saw what’s possible and where value actually gets created, and where you cannot add any more value, where all you have to do is get things done as soon as possible.” Stage gate, taught properly, “can give you access, tools, language, and conversations” that help leaders make confident, informed decisions.

Key moments
  1. The QA engineer’s job, described exactly: implement the project quality management system, then audit the project against contractual requirements, international standards and organizational policy.~10:40
  2. The moment the reports stopped meaning anything. “My audit reports after a while begin to be the same… I didn’t really feel like I’m making a big difference.”~12:40
  3. Orion brings in a mutual colleague, Akin Oni, and a title that has become shorthand in the space: The Operation Was Successful But The Patient Died. “You can follow all the procedures and still have high quality scores, but these projects were not actually being successful for the organizations.”~15:00
  4. Iwona extends the metaphor to contracting: “if the patient goes for a surgery and then dies at the end, it’s the family which will take the consequences. It’s not often the doctor that is following their own procedure and their own framework.”~16:30
  5. Who is actually accountable. “It’s the owner that has responsibility to set a project for success, because the owner focus is always long-term: how can we create with that project real value for the community, the environment, the organization itself.”~17:00
  6. The blunt corollary: “When I talk to construction companies, they are not that interested in stage gate process, because if there is a change, they just gonna ask the client to pay.”~17:45
“A good governance should improve the quality of your decisions. It’s not just about generating more documents. It’s not just about even document quality. It’s really about enabling leaders to make good decisions.”Iwona Wilson · ~14:40
She brings receipts This is not a consultant’s theory about compliance culture: it is a former auditor describing her own reports and why they stopped satisfying her. The distinction between an approval system and a decision-making system, which becomes the episode’s title, is built on those years of audits.
Chapter 04 · Act II · 18:00

From Deliverables to Decisions

If compliance isn’t confidence, what changes? Iwona is careful about attribution first: much of this comes from Robert Cooper on stage gate and from decision science, now taught as decision quality and promoted by the Society of Decision Professionals. Then she names the shift: most organizations structure projects around deliverables, templates and checklists, and the decision gate process asks them to structure around decisions instead. That single reframe changes what a team is asked to produce.

“The only reason we have phases is to prepare you for the next decision you need to make. The only reason you’re asked to produce deliverables is to enable some kind of decision.”Iwona Wilson · ~19:50

The waste this creates

“A lot of projects often get stuck, and they produce deliverables after deliverables without pausing to ask the question: what is the decision that we actually need to make? That’s gonna create a lot of unnecessary waste in terms of time and resources, and might lead to a lot of deliverables getting produced with no value for leadership to make the decision.”

What decision quality actually measures

“Decision quality is a standalone discipline that is measuring the quality of decisions you need to make based on the information you have available at the given time, regardless of the outcomes the decision is going to lead to.” The point that lands: a decision can be high quality and still turn out badly, and a lucky outcome does not make a decision good.

Key moments
  1. Attribution, unprompted: stage gate from Dr. Robert Cooper; decision-making and opportunity framing from decision science, “which we really call now decision quality, promoted by organizations like the Society of Decision Professionals.”~18:30
  2. What leadership is actually there to understand at a gate: the decision, the options considered, where the information came from and whether it’s current, the value, the trade-offs, the logic behind the recommendation, and the commitment being asked of them. The six dimensions, introduced in passing.~21:00
  3. The failure mode named: “those organizations that still run the gate reviews heavily focused on activities and deliverables often lose the focus of what’s the intent of the gate review.”~22:00
  4. Orion asks the practitioner’s question: is the gate decision always proceed / recycle / hold / stop, or do secondary decisions get brought to a gate?~22:20
  5. The minimum-work principle. “What’s the minimum amount of work that we need to do to answer the main question at gate one? It’s not about doing all possible deliverables that we’ve ever done in our life.”~25:15
  6. The Fort Myers land analogy arrives (a block of land in Florida while you live in Oregon) and never leaves the episode.~25:45
“Ultimately, at every decision gate an organization is making two decisions. The first is: are we ready? Have we done what we said we would, assured the deliverables, answered the key decisions, tested the assumptions? And the second is: do we want to proceed? Which is more a business decision, given the market, given our strategy, given the current pricing, given what else is going on.”Iwona Wilson · ~28:15
Don’t miss The two-decisions framing at ~28:15 is the most portable idea in the chapter. Most gate packs answer only the first question (are we ready) and treat the second as a formality, which is exactly how a project with a perfect readiness score gets approved into a market that no longer wants it.
Chapter 05 · Act II · 29:00

Where Projects Are Won or Lost

Orion had planned to ask which decision matters most. The Florida analogy makes him rethink the question, and Iwona answers the version he didn’t quite ask. Everyone points at FID because that is the decision that goes public and releases the money. Her position is more precise than “the early stuff matters too”, and it is the sentence her book is named after.

“All decisions are equally important, but not all decisions have the same consequences. All decisions are very important, and they need to be answered. If they are not answered consciously, they’re answered unconsciously, through assumptions.”Iwona Wilson · ~32:15

Why the early gates are underestimated

“Many projects are already lost or won before that decision, and it’s really about how they treat those early decisions.” After assess and after concept is when leadership has to be crystal clear on what the opportunity is, what’s driving it, and what assumptions are being made about the present and the future. “This is where we’re often locking in our options, and that’s why those early decisions are often underestimated.”

What FID actually locks

“Once you pass the FID stage, it gets so much more expensive, plus it’s almost impossible to change. You are emotionally committed to your decision. The whole family and community already knows that you are now Floridian, so you’re politically connected to that decision and financially invested in that decision.” Three commitments, not one: emotional, political, financial.

Key moments
  1. Why everyone believes FID is the most important gate: it’s when the project becomes public, when the most funding is released, and when the decision is treated as irreversible.~31:20
  2. The reframe (equal importance, unequal consequences) and the assumptions that fill the gap when a decision isn’t made consciously.~32:15
  3. Cheapness of change as the real argument: “when you’re gonna change your mind, change directions, new information is gonna become available, making changes at that stage is way cheaper than committing to change once you’re on the plane moving your family to Florida.”~33:40
  4. The payoff for doing early work well: a far more confident FID, with a clear story of the options considered, the target outcome and how the decision was made. “So it’s easy to create the story for the public: why do we think this is the right thing to do?”~34:30
  5. Orion’s counter-point, which she accepts: killing a project in assess is not wasted work; it tells the organization something worth knowing. “It helps me know where I’m gonna be spending my life and where to invest more energy.”~30:00
Worth pausing on The Florida analogy is doing real work, not decoration. It smuggles in the thing that makes early decisions hard: they are made by people who will personally have to live with them, in front of people whose opinion they care about. Governance frameworks rarely account for that; framing workshops are built for it.
Chapter 06 · Act II · 35:00

When Gate Reviews Become Theater

Two practical questions from Orion, aimed squarely at the executive listening. First: how do I set my team up with this mindset, when most engineers are deeply process-focused? Second, and sharper: how do I spot when a gate review looks healthy and isn’t? Iwona is explicit that she doesn’t run gate reviews (her work is upstream, framing opportunities and setting teams up for them), which is precisely why her warning signs are behavioural rather than procedural.

“How do we provide this grounding presentation? Is everything super polished? Do people ask questions? Do they challenge assumptions? Or do they just accept everything without any challenge?”Iwona Wilson · ~41:20

Start with your own current state

Before changing anything, get present with what you already have. “Get individuals together from different parts of the business, and run a little bit of a lessons learned workshop to understand what are some of the patterns running through your organization. What is currently happening? What are some of the processes that are already working for you? What aren’t working for you, and why?”

Then audit each element

Go element by element through the decision gate process: how gate review meetings run, how each phase starts, how projects are categorized and scaled, how inputs from different functions are invited, how teams are aligned on the work ahead, how uncertainty is reduced phase to phase, and whether assurance is actually producing insight that supports confident decisions.

Key moments
  1. Know your role first: what the organization is for, what it expects from its projects, and whether you are the owner initiating projects or a party executing them. The answer changes everything downstream.~36:10
  2. The structure and agenda of the meeting itself “has a lot to do with how we establish a safe and also brave space for discussion.”~41:00
  3. Warning sign: at a second gate review, someone names a stakeholder who has never come up before. “Then you might know that probably stakeholder engagement have been done too late.”~42:10
  4. Warning sign: the meeting is mostly about how many documents are done and what their status is, rather than a conversation that improves the decision leadership is about to make.~42:30
  5. What a healthy team can do on demand at a gate: explain what the opportunity is about, name the major value driver, state the assumptions behind the selected option, and identify the biggest risk.~42:00
  6. The test for whether governance is working at all: “are leadership teams getting information that gives them clarity and confidence to approve those projects, so they can move forward, and kill those projects that are just badly framed projects?”~38:45
“There’s a lot that you can listen to and just watch, by listening to the quality of those conversations. And those warning signs might lead to a false confidence about the project.”Iwona Wilson · ~43:00
Don’t miss Every warning sign she gives is available to an executive who simply sits in the room and listens: no dashboard, no maturity assessment, no consultant. Being “the fly in the room” at a gate review is, on her account, the cheapest governance diagnostic available.
Chapter 07 · Act II · 44:00

The Groan Zone

The longest and best stretch of the episode. Iwona explains why a traditional meeting is the wrong instrument for framing a complex opportunity, brings in Sam Kaner’s research on group decision-making to name the messy middle, and defends discomfort as a design feature rather than a facilitation failure. Then she does something unusual on a governance podcast: she describes how she and her husband run the same process at their own kitchen table, with Post-it notes.

“An opportunity framing workshop can be really messy, and can be painful, and they can be uncomfortable. But this is the cost of alignment.”Iwona Wilson · ~49:00

Why traditional meetings can’t do this

They are well designed to bring people together for a status update, not to make important decisions, explore a problem, or frame a big opportunity with a lot of moving parts. “If you bring a bunch of people together, people are usually not on their best behavior. They tend to protect their own interests, especially if you bring functional managers from different functions together.” And they self-censor: when the culture says “we’ve already covered this,” or “let’s keep it simple,” concerns stop being voiced.

What the facilitator is for

“You need someone with no vested interest in the outcome, that would purely be interested in helping the group go through the process”, carrying the team through the groan zone so they land with shared understanding of what they’re trying to achieve and what decision needs to be made. The neutrality is the qualification, not a nice-to-have.

Key moments
  1. Sam Kaner’s three-part structure: diverge (invite opinions and questions); then somewhere in the middle, tension; then converge (narrow the thinking, plan the action, make the decision).~45:50
  2. The groan zone, and what leaders do when they hit it. “It gets messy. People feel the disagreement, discomfort… So what they do that moment, they say, ‘Well, let’s stop. Let’s schedule the next meeting for next week.’”~46:40
  3. The cost of avoiding it: “that’s why strategy meetings often take three months. If they could actually take one day or two days.”~47:20
  4. The claim that makes the discomfort worth it: “those teams that are able early on to go through those difficult conversations, the conflicts, those teams tend to execute faster with less surprises.”~47:50
  5. Orion connects it to forming, storming, norming, performing, and asks whether a conflict-avoidant team can even reach a good decision. Iwona’s answer: in the assess phase you don’t have a team yet, so the model applies less than you’d think.~49:20 → ~53:30
  6. The kitchen table method: “We take Post-it notes, me and my husband. We don’t sit opposite to each other. In fact, we don’t even look at each other, and we quietly write down what are some of the issues, questions, and concerns that we see in this coming opportunity.” Then they categorize, then they walk the wall. “We’re trying to get our thoughts out of our heads and make them visible on the wall.”~51:30
  7. Why framing is avoided in siloed organizations (different functions, different priorities, no willingness to come together) and why doing it consistently changes the culture rather than just the project.~53:50
  8. Challenger. Orion asks about the O-ring and the management override of the people on the ground. Iwona: “If people down on the ground are not invited to express their opinions, that is gonna impact decision-making. That is gonna often show up later on as a surprise that could have been prevented.”~57:45
  9. Her recommendation, stated flatly: “my recommendation is that every project has an opportunity framing workshop”, with operations, execution, regulatory, community, project controls, project management and HSE experience all in the room early.~58:20 → ~1:00:00
“If people don’t feel like they can contribute, they begin to disengage. They lose the trust in the process. They lose the trust in the governance, and then they often leave.”Iwona Wilson · ~55:40
Worth pausing on The Post-it story is the most practical thing in the episode and the easiest to dismiss because it sounds domestic. The mechanic is real: write silently and in parallel before speaking, so that everyone is fully self-expressed before anyone is defending anything. “So often people lack a process where they can fully self-express themselves in the most efficient way.”
Chapter 08 · Act II · 1:01:00

Six Dimensions of Decision Quality

Orion admits he doesn’t know what the six dimensions are and asks whether he should have. Iwona walks the decision quality wheel one dimension at a time, and pre-empts the objection she always gets, which is that all six are obvious.

“A lot of people listen to those dimensions and they say, ‘Iwona, this is such common sense. Why are you even telling me this?’ Because it is so much common sense. And I often say that the biggest challenge is if the common sense isn’t applied early enough.”Iwona Wilson · ~1:02:20

The rule · a decision is only as good as its weakest dimension

Key moments
  1. What the wheel is for: it is a method you can use to measure alignment across the six dimensions before a major decision is made, or soon after, to check the quality of the one you made.~1:02:40
  2. The six, in her order: appropriate frame, creative alternatives, relevant information, values and trade-offs, sound logic, commitment to action.~1:02:45 → ~1:03:40
  3. The weakest-link rule. “So the quality of decision is as good as the weakest.”~1:03:50
  4. The two ways it breaks. “You might understand the trade-offs. You might understand where the information comes from. But if there’s no commitment, nothing happens.” And in reverse: “You might even have a commitment, but if you have poor quality information, if you’re making wrong assumptions, the quality of that decision will be really low, and the impact it will have will be damaging.”~1:04:00
  5. The commitment question, made concrete: “who are the key stakeholders that need to be involved? What amount of commitment is required to make that decision stick?”~1:05:50
  6. Where else it works: “you can actually get together with your team in any function, whatever decision you’re gonna make, and just go over those six and discuss it with your team before you make a decision or soon after.”~1:04:40
Don’t miss Orion tries to play the six back from memory at ~1:05:00 and gets most of them. It is worth listening to because it demonstrates the actual claim: the dimensions are simple enough to hold in your head after hearing them once, which is exactly why nobody bothers to check them.
Chapter 09 · Acts III–IV · 1:06:00

The Takeaway & the Billion-Dollar Math

Orion offers his own takeaway first: that decision-making can’t live only at the gates, and that the real prize is opportunity framing bubbling up organically through the rest of the organization. Then he asks Iwona for hers, and closes the loop by putting a number on the stakes.

“You need to aim to create some sort of language fluency across different functions, so we all speak from the same hymn sheet and we understand the decision gate process language. And you also need a framework for decision-making that people trust, that empowers individuals inside those teams to voice their opinion, and enables decision-makers to make good, confident decisions.”Iwona Wilson · ~1:08:10

Orion’s takeaway

“If you’re a really high performing organization, it seems to me that decision-making is not just at these gates. It’s actually something that needs to be inculcated into the entire organization somehow. And if you can actually find a way to work that same opportunity framing into the rest of your organization and your teams, and it’s organically bubbling up, that really is the prize.”

Iwona’s takeaway

Three things, in order: look honestly at the decision gate mindset your organization actually has; build language fluency across functions so everyone means the same thing by the same words; and give people a decision-making framework they trust enough to speak up inside.

The stakes, as Orion frames them

“For a billion-dollar project… if you do ten billion-dollar projects, you will expect five of them to overrun, and your average of those overruns is gonna be about $500 million. So when you budget a billion-dollar project, you budget an average overrun of $500 million. That’s how bad our decision making is in this space, but it’s also just the opportunity that’s on the table if you have good decision making.”

Editorial note on that figure

Orion cites these numbers from memory on air. He says as much: “I think I looked these numbers up a little while ago.” Treat them as directional rather than as a sourced statistic. The order of magnitude is consistent with the published megaproject literature on cost overrun frequency and severity, but the specific 50% / $500M pairing is not attributed to a study in the conversation and should not be quoted as one.

Key moments
  1. Iwona’s takeaway: mindset, language fluency, and a framework people trust.~1:07:40
  2. Orion’s framing of the gravity: “something we probably should have told people in the beginning.”~1:08:50
  3. The upside argument: getting decision-making right “could make a huge difference between an organization surviving or not, in many ways.”~1:09:45
Chapter 10 · The title exchange · 1:32:00

The Capability Gap

This is the exchange the episode takes its name from. Orion puts the question that had been on his list all along: everybody in major capital projects says they have a stage gate process, so why do we keep seeing billion-dollar surprises? Iwona’s answer is the sentence the whole conversation has been building toward, and then she does something better than restate it: she describes the two opposite ways process maturity goes wrong.

“Companies do have stage gate process in place, but they still experience project overruns, cancellation, or they create projects with not enough value based on what they wanted. And that is happening because having a process in place is not the same as having capabilities. That’s the biggest misconception in this industry.”Iwona Wilson · ~1:33:10

What organizations have

“Some phases, some gates, maybe some templates, maybe approval lists, maybe even mandatory checklists for the gate review.”

What is missing

“Very few organizations actually teach how to think through uncertainty, how to frame opportunities, how to create alignment around key stakeholders, how to identify, name, and challenge assumptions, how to make quality decisions, how to understand when a project is heading in the wrong direction.”

Key moments
  1. When companies actually call. “Many companies ask about stage gate process usually after something major happens, after a major overrun, or some big public issue, or investor pressure or community pressure, or change of leadership, or some operational underperformance that happens over a long time.”~1:34:40
  2. The distinction, named. “That’s usually when they begin to see there is a difference between having an approval system and having a decision-making system.”~1:35:10
  3. The knowledge gap between the mature majors and the fast-growing companies that have never developed a project: the ones who “tend to run into execution, skip stakeholders alignment, skip option analysis, and are often not clear around the real value of what they’re trying to achieve.”~1:35:40
  4. Orion’s good question: can you backslide on capability while keeping the process? Which opens the second failure mode.~1:36:40
  5. The over-developed end. “A lot of them, with well-defined stage gate process, develop so much in the process that the process gets very bureaucratic”: massive document production, impossible gate requirements, excessive approvals, lengthy decision cycles. “And then the conversation on the project team, rather than how can we improve decision quality, is all about how can we pass the gate.”~1:37:30
  6. What that does to people: “people begin to lose trust in the process, they detach, and they produce documents to ensure compliance as opposed to create clarity.”~1:38:30
  7. The best-kept secret. Opportunity framing “is usually only known by the top companies in oil and gas, Chevron, Shell, Woodside”: companies that have matured their stage gate for three or four decades and use framing “not just as a best practice, but as a mandatory approach to start the initiatives.”~1:38:50
  8. Outside those organizations: “teams rely on individual experiences. They assume alignment. They don’t test the alignment. They call assumptions givens. They don’t challenge them.”~1:39:50
  9. Why stage gate emerges at all: “most organizations really started stage gate process because they started looking at more than one project. And when you have more than one project, you really need to be cautious where you’re going to invest.”~1:42:20
  10. Orion’s aside on organizations that wait until they’re big enough (“the 10,000 employee organization definitely started the stage gating before they reached that size”) and Iwona’s reply for the smaller companies: leverage the principles now rather than waiting.~1:41:00 → ~1:43:00
“Move from developing faster to developing smarter. That’s really what I think: that’s where the opportunity is.”Iwona Wilson · ~1:43:00
She brings receipts The capability list at ~1:34 is worth treating as a checklist. Read it against your own organization item by item (thinking through uncertainty, framing opportunities, creating stakeholder alignment, naming and challenging assumptions, measuring decision quality, recognising a project heading the wrong way), and note how many of the six are taught anywhere in your process documentation, as opposed to assumed.
The line that closes it

“Some people would even say that your success is only one decision away.” ~1:44

Concepts, Drawn Out

The Big Ideas

Three ideas carry the episode. Sketched here the way a framing facilitator would whiteboard them at the front of a room, plus a fourth, the decision quality chain, drawn in chapter 08 where it belongs.

1 · An approval system and a decision-making system are not the same building

Two organizations can hold identical process documentation and be doing completely different things with it. What separates them is not the framework: it is the set of capabilities that make the framework mean something. That set is what almost nobody buys, teaches or measures.

An approval system
  • Phases and gates on a wall chart
  • Templates and guidelines
  • Approval lists and mandatory checklists
  • Deliverable status as the gate conversation
  • The question is: can we pass?
Capability The missing span
A decision-making system
  • Thinking through uncertainty
  • Framing opportunities before they’re projects
  • Aligning stakeholders across functions
  • Naming and challenging assumptions
  • The question is: is this a good decision?
From Iwona’s answer at ~1:33–1:35 · “having a process in place is not the same as having capabilities”
2 · All decisions are equally important. Not all carry the same consequences.

The organization’s attention follows the money, which means it arrives exactly when changing your mind has become most expensive. The leverage sits in the quadrant nobody is watching.

← cheap to change, nobody watching  ·  expensive to change, everybody watching →
Assess

Cheapest to change · lowest attention. What is the opportunity, what’s the value proposition, is there at least one way to realize it? Highest leverage in the whole lifecycle.

Develop → FID

Expensive to change · attention arriving. Concept locked, estimate built on framing assumptions, the story being written for the public.

Concept / select

Still cheap to change · still private. Options generated and analysed, value drivers tested, one alternative chosen. Options quietly get locked here.

Execute

Near-irreversible · maximum attention. Emotionally, politically and financially committed. “The contractor just gonna send you an invoice.”

within each column, the lower cell is later in the lifecycle
From Iwona at ~32:15 and ~33:40, and the title of her book, Where Projects Are Won or Lost
3 · The groan zone is not a facilitation failure

Diversity in the room produces tension; tension is what shared understanding is made of. The only real choice is whether you pass through it in two days with a neutral facilitator, or over three months of rescheduled meetings.

Diverge Invite opinions Ask questions Surface concerns
The groan zone Disagreement · discomfort · mess
Converge Shared understanding · the decision named · faster execution with fewer surprises
From Iwona at ~45:50–49:00, citing Sam Kaner’s research on collaborative group decision-making · “this is the cost of alignment”
Bonus · “The One Skill Every Future Project Leader Needs” · 34 min

From the Bonus Episode

The companion episode turns from governance to the people who will inherit it. Orion asks what advice Iwona would give a student watching who wants into this space, and the answer has nothing to do with software or certifications. Quotations below are her own words, lightly condensed, with approximate positions in the full recording; the split between the main and bonus cuts is Orion’s edit, so a line’s exact position in the published bonus will differ.

“Seek opportunities where you can polish your critical thinking skills. This is what I love the most about opportunity framing, where people see there is a distinction between a given and an assumption. When people see that actually a lot of the stuff can be negotiated.”Iwona Wilson · bonus material, recording ~1:11

Why critical thinking, and why now

“If I think about the next generation of leaders and what would be really useful for them, given the challenges that we have in most countries, as well as the rise of AI, I would say seek opportunities where you can polish your critical thinking skills.”

Bonus material · recording ~1:10:50

Where to go and find it

“I know that University of Houston, for example, they have their own chapter, Society of Decision Professionals, and they’re always open to bring new people on board. They collaborate with the industry, with large organizations, with myself, bringing different individuals who teach students some of those decision-making tools that they can apply in their life.”

Bonus material · recording ~1:12:10

The AI line she won’t cross

“If we let AI make decisions for us, there are still consequences that will have to be absorbed: the project, the organization, the teams will be impacted. And the AI is not gonna pay for whatever’s gonna come out of our decisions.”

Bonus material · recording ~1:16:20

Where AI does earn its place

“AI can definitely speed up a lot of the tasks that we do. It can help with brainstorming, by helping to categorize and organize our thoughts. So I can see ways even inside the workshop where we can save some time by adding an AI component… but making sure that technology is not ahead of the humans.”

Bonus material · recording ~1:18:00

What framing gives a young engineer

“There’s nothing more empowering for young individuals than giving them tools so they can make their own decisions confidently… and really be the one who knows how to ask important questions before those decisions are made.”

Bonus material · recording ~1:12:40

The unexpected turn

“I go a little bit against the foundation in decision analysis that everything needs to be logical, because I do think that you can also attract good luck for your project. You can attract the right stakeholders and contractors… Create that excitement for what it is that you’re trying to achieve. Be very clear on intention. Allow people to contribute. But at the same time, detach: if it’s not the right time, don’t get upset about it.”

Bonus material · recording ~1:22:40 and ~1:24:40

Don’t miss At ~1:25 she connects that turn straight back to governance, and it is sharper than it first sounds: the first phases of a project are historically confidential (“this is our own in-house opportunity”), and she notes that infrastructure projects increasingly break that confidentiality early because of political pressure, which loads external consequence onto decisions that were supposed to be cheap to change. “We wanna make sure that we plant the right seed before we see the benefits.”
Quick Reference

Quote Bank

The best on-the-record lines, gathered in one filterable place. “Highlight” marks the lines most worth scrubbing back for. Quotes are lightly condensed with meaning untouched; timestamps are approximate positions in the full recording.

The Quality Route In 0:00–3:30

  • “I got into the oil and gas industry and the capital projects through quality assurance, actually.”Iwona Wilson · ~1:15
  • “At that time, quality assurance and ISO 9001 was a really big thing, and for me it was a way for organizations to become more competitive, to boost their performance, build trust with customers, and really win a lot of work.”Iwona Wilson · ~1:40
  • “I really like drinking beer. However, I had this realization that working at the brewery and smelling hops every day wasn’t really something I loved.”Iwona Wilson · ~2:10

Decision Gate 101 3:30–9:15

  • Highlight“The idea is very simple. It’s really about moving an idea from the early thinking into the execution whilst reducing the uncertainty, the unknown that exists in a project.”Iwona Wilson · ~4:20
  • “During the gate the leadership would pause and would ask the question: ‘Given all we know about the opportunity, do we still want to continue investing in this project?’”Iwona Wilson · ~5:00
  • “The final investment decision, that’s when the organization announces they have a project, and they ask the question, ‘Are we truly ready to execute this project?’”Iwona Wilson · ~7:05
  • Highlight“Stage gate is seen as a governance tool, and it is a governance tool. But for me, it’s really more a decision-making system, and also it’s a way of thinking.”Iwona Wilson · ~8:15
  • “That was like an entire course. If you have someone starting on a major project, we could just clip that and give it to them.”Orion Matthews · ~9:00

Compliance Isn’t Confidence 9:15–18:00

  • Highlight“Most projects were compliant. They follow procedures. They use the right templates. The boxes get ticked. But many of those projects would experience challenges, and some of them would be even cancelled, and somehow I never really knew why.”Iwona Wilson · ~11:20
  • Highlight“Projects might pass gates, and might still carry political bias, or hidden assumptions, and might still pass the gate with stakeholders being misaligned, if the focus is so much about passing the gate as opposed to improving decision-making during the gate.”Iwona Wilson · ~12:10
  • “My audit reports after a while begin to be the same. They would report on the same issues around document control, communication, interfaces… I didn’t really feel like I’m making a big difference.”Iwona Wilson · ~12:40
  • Highlight“A good governance should improve the quality of your decisions. It’s not just about generating more documents.”Iwona Wilson · ~14:40
  • “It’s the owner that has responsibility to set a project for success, because the owner focus is always long-term.”Iwona Wilson · ~17:00
  • “When I talk to construction companies, they are not that interested in stage gate process, because if there is a change, they just gonna ask the client to pay.”Iwona Wilson · ~17:45

From Deliverables to Decisions 18:00–29:00

  • Highlight“The only reason we have phases is to prepare you for the next decision you need to make. The only reason you’re asked to produce deliverables is to enable some kind of decision.”Iwona Wilson · ~19:50
  • “A lot of projects often get stuck, and they produce deliverables after deliverables without pausing to ask: what is the decision that we actually need to make?”Iwona Wilson · ~20:10
  • “Decision quality is a standalone discipline that is measuring the quality of decisions based on the information you have available at the given time, regardless of the outcomes the decision is going to lead to.”Iwona Wilson · ~20:40
  • “What’s the minimum amount of work that we need to do to answer the main question at gate one? It’s not about doing all possible deliverables that we’ve ever done in our life.”Iwona Wilson · ~25:15
  • Highlight“At every decision gate an organization is making two decisions. Are we ready to proceed, and do we want to proceed?”Iwona Wilson · ~28:15

Where Projects Are Won or Lost 29:00–35:00

  • Highlight“All decisions are equally important, but not all decisions have the same consequences.”Iwona Wilson · ~32:15
  • Highlight“If they are not answered consciously, they’re answered unconsciously, through assumptions.”Iwona Wilson · ~32:25
  • “Many projects are already lost or won before that decision, and it’s really about how they treat those early decisions.”Iwona Wilson · ~32:40
  • “Once you pass the FID stage, it gets so much more expensive, plus it’s almost impossible to change. You are emotionally committed to your decision.”Iwona Wilson · ~34:00
  • “Making changes at that stage is way cheaper than committing to change once you’re on the plane moving your family to Florida.”Iwona Wilson · ~33:50

When Gate Reviews Become Theater 35:00–44:00

  • Highlight“Is everything super polished? Do people ask questions? Do they challenge assumptions? Or do they just accept everything without any challenge?”Iwona Wilson · ~41:20
  • “If all of a sudden someone mentions a stakeholder that hasn’t been mentioned earlier on, then you might know that probably stakeholder engagement have been done too late.”Iwona Wilson · ~42:10
  • “Run a little bit of a lessons learned workshop to understand what are some of the patterns running through your organization.”Iwona Wilson · ~37:15
  • “Are leadership teams getting information that gives them clarity and confidence to approve those projects, so they can move forward, and kill those projects that are just badly framed projects?”Iwona Wilson · ~38:45
  • “Those warning signs might lead to a false confidence about the project.”Iwona Wilson · ~43:00

The Groan Zone 44:00–1:01:00

  • “If you bring a bunch of people together, people are usually not on their best behavior. They tend to protect their own interests.”Iwona Wilson · ~44:50
  • “They often self-censor themselves… because the culture of the organization is, ‘Let’s keep it going. Let’s move on.’”Iwona Wilson · ~45:30
  • Highlight“He calls it the groan zone. It gets messy. People feel the disagreement, discomfort. And a lot of leaders don’t like sitting in that place, so they say, ‘Well, let’s stop. Let’s schedule the next meeting for next week.’”Iwona Wilson · ~46:40
  • “And that’s why strategy meetings often take three months. If they could actually take one day or two days.”Iwona Wilson · ~47:20
  • Highlight“Those teams that are able early on to go through those difficult conversations, the conflicts, those teams tend to execute faster with less surprises.”Iwona Wilson · ~47:50
  • Highlight“An opportunity framing workshop can be really messy, and can be painful, and they can be uncomfortable. But this is the cost of alignment.”Iwona Wilson · ~49:00
  • “We take Post-it notes, me and my husband. We don’t sit opposite to each other. In fact, we don’t even look at each other, and we quietly write down what are some of the issues, questions, and concerns.”Iwona Wilson · ~51:30
  • “We’re trying to get our thoughts out of our heads and make them visible on the wall.”Iwona Wilson · ~52:15
  • “If people don’t feel like they can contribute, they begin to disengage. They lose the trust in the process, and then they often leave.”Iwona Wilson · ~55:40
  • Highlight“If people down on the ground are not invited to express their opinions, that is gonna impact decision-making. That is gonna often show up later on as a surprise that could have been prevented.”Iwona Wilson · on the Challenger question · ~58:40

Six Dimensions of Decision Quality 1:01:00–1:06:00

  • “A lot of people listen to those dimensions and they say, ‘Iwona, this is such common sense.’ … The biggest challenge is if the common sense isn’t applied early enough.”Iwona Wilson · ~1:02:20
  • Highlight“So the quality of decision is as good as the weakest.”Iwona Wilson · ~1:03:50
  • Highlight“You might understand the trade-offs. You might understand where the information comes from. But if there’s no commitment, nothing happens.”Iwona Wilson · ~1:04:00
  • “Who are the key stakeholders that need to be involved? What amount of commitment is required to make that decision stick?”Iwona Wilson · ~1:05:50

The Takeaway & the Billion-Dollar Math 1:06:00–1:10:00

  • Highlight“You need to aim to create some sort of language fluency across different functions, so we all speak from the same hymn sheet, and a framework for decision-making that people trust.”Iwona Wilson · ~1:08:10
  • “Decision-making is not just at these gates. It’s actually something that needs to be inculcated into the entire organization somehow… that really is the prize.”Orion Matthews · ~1:07:00
  • “When you budget a billion-dollar project, you budget an average overrun of $500 million.”Orion Matthews · cited from memory, directional · ~1:09:30

The Capability Gap 1:32:00–1:44:00

  • Highlight“Having a process in place is not the same of us having capabilities. So that’s the biggest misconception in this industry.”Iwona Wilson · ~1:33:20
  • Highlight“Very few organizations actually teach how to think through uncertainty, how to frame opportunities, how to create alignment around key stakeholders, how to identify, name, and challenge assumptions.”Iwona Wilson · ~1:34:00
  • “Many companies ask about stage gate process usually after something major happens, after a major overrun, or some big public issue, or investor pressure or community pressure, or change of leadership.”Iwona Wilson · ~1:34:40
  • Highlight“That’s usually when they begin to see there is a difference between having an approval system and having a decision-making system.”Iwona Wilson · ~1:35:10
  • “The conversation on the project team, rather than how can we improve decision quality, it’s all about how can we pass the gate.”Iwona Wilson · ~1:38:10
  • “People begin to lose trust in the process, they detach, and they produce documents to ensure compliance as opposed to create clarity.”Iwona Wilson · ~1:38:30
  • “Opportunity framing is still one of the best-kept secrets in the oil and gas industry.”Iwona Wilson · ~1:38:50
  • Highlight“They assume alignment. They don’t test the alignment. They call assumptions givens. They don’t challenge them.”Iwona Wilson · ~1:39:50
  • Highlight“Move from developing faster to developing smarter. That’s where the opportunity is.”Iwona Wilson · ~1:43:00
  • Highlight“Some people would even say that your success is only one decision away.”Iwona Wilson · ~1:44:20

From the Bonus Episode “The One Skill Every Future Project Leader Needs”

  • Highlight“Seek opportunities where you can polish your critical thinking skills.”Iwona Wilson · bonus material, recording ~1:10:50
  • “This is what I love the most about opportunity framing, where people see there is a distinction between a given and an assumption.”Iwona Wilson · bonus material, recording ~1:11:20
  • Highlight“If we let AI make decisions for us, there are still consequences that will have to be absorbed. And the AI is not gonna pay for whatever’s gonna come out of our decisions.”Iwona Wilson · bonus material, recording ~1:16:20
  • “Making sure that technology is not ahead of the humans.”Iwona Wilson · bonus material, recording ~1:18:30
  • “There’s nothing more empowering for young individuals than giving them tools so they can make their own decisions confidently.”Iwona Wilson · bonus material, recording ~1:12:40
  • “Create that excitement for what it is that you’re trying to achieve. Be very clear on intention… But at the same time, detach. If it’s not the right time, don’t get upset about it.”Iwona Wilson · bonus material, recording ~1:24:40