PodBOK brings industry guidance together with real-world experience from major projects. Use it to inform your approach, and check the facts and requirements that apply to your project.
Start with the work your team must deliver
A project director needs people who can turn an investment into a working asset. That means more than filling the management boxes: someone must define the requirements, design the solution, secure workable access, buy the right equipment, organise construction and prepare the operating team. Someone also needs to connect those contributions when they disagree.
Start with the capabilities and decisions the project needs, then decide how to provide them. The right mix depends on the asset, location, delivery model and phase. Expertise may sit with the owner, a designer, a delivery partner, a contractor, a supplier or a shared function. A name on the organisation chart does not establish that the skill, capacity or authority is available.
For each capability, record the work product, accountable owner, decision rights, interfaces, capacity and date needed. Then decide whether to develop, transfer, recruit or contract for the expertise. Confirm the allocation against project governance and contracts.
Green Riyadh: let the project shape the team
Jovita Stander's Green Riyadh conversation shows why a generic staffing list is only a starting point. Speaking about her experience as Project Control Director, she describes GIS and graphic designers within her controls remit. Elsewhere in the programme, the tree management office drew on landscape engineers, GIS and technical specialists. These were different contributions to an urban-greening programme, not one interchangeable group of designers.
The lesson for a director is to look for the expertise the asset and its stakeholders demand. Graphic design helps communicate a project; landscape and engineering design shape what is built. GIS can connect spatial information with planning. Decide what each contribution must achieve and where it needs to connect.
Give design and engineering real ownership
Name who owns the overall design, who develops each component and who resolves the interfaces. A design manager coordinating outputs, a discipline designer developing a solution and a person authorised to accept a technical decision may be different people. Make those responsibilities clear across consultants, suppliers and the owner.
- Choose disciplines from the asset and its risks. Consider civil, structural, mechanical, electrical, process, architecture, software and systems expertise where the work needs them.
- Bring site and asset specialists into the relevant decisions. Landscape, soils, ecology, water or irrigation expertise may matter on some projects; other assets will need a different mix.
- Agree the design handoff. Identify the requirements, maturity, interfaces and approved information the next team needs before it can purchase, build or test.
- Include construction, maintainers and operators in design reviews early enough for their knowledge to change the solution. Name who records and resolves conflicting requirements.
A capability map for the project director
Use this map to look for gaps, then tailor it to the work. One person may cover several functions; a large programme may have many teams within one row. For each row, check that the contribution is covered and its handoffs have an owner.
Scroll sideways or use the arrow keys to see all columns.
| Capability | Roles or disciplines to consider | Responsibility and critical handoff |
|---|---|---|
| Investment and delivery leadership | Sponsor / asset owner, project director, project managers, finance and business-case support | Translate the investment purpose into outcomes, decisions and escalation routes. Connect the sponsoring organisation with those delivering and operating the asset. |
| Requirements, design and engineering | User representatives, design manager, chief engineer or architect, discipline designers and interface specialists | Define what the asset must do and integrate the design. Name who owns component outputs, resolves interfaces and agrees acceptance conditions with the receiving team. |
| Site, environment and external commitments | Survey, geotechnical, environmental, ecology, land/access, permitting, stakeholder and utility specialists as relevant | Understand the setting and constraints before they block design or execution. Connect site information, community commitments, consents and the delivery plan. |
| Commercial and supply chain | Procurement, supply chain, contracts/commercial, legal advisers and package owners | Align specifications, purchasing, supplier commitments and contractual administration with the work the delivery team needs. Maintain a clear owner for changes and follow-up. |
| Planning, cost and risk | Project controls manager, planners/schedulers, estimators, cost controllers, risk and change specialists | Produce a consistent plan, forecast and basis for decisions. Agree assumptions and reporting dates with delivery leads, finance and leadership. |
| Construction and work readiness | Construction managers, supervisors, workface planners, trades, logistics and temporary-works specialists as relevant | Prepare executable work with materials, access, methods and information ready. Bring field knowledge into design and procurement decisions. |
| Safety, quality and assurance | HSE, quality, inspection/testing and independent review specialists where required | Define the checks, evidence and escalation needed for the work. Keep delivery responsibilities, specialist advice and acceptance authority explicit. |
| Commissioning and the operating organisation | Commissioning leads, operations readiness, operators, maintainers and training specialists | Plan testing, acceptance, operational capability and handover information. Involve the receiving organisation early enough to influence the asset it will run. |
| Data and controlled information | Data/reporting, document control, digital/BIM/GIS, IT and AI specialists where relevant | Keep definitions, records, approvals and information transfers usable and traceable. Assign source ownership and the skills to manage information through its lifecycle. |
| Communication and visual explanation | Stakeholder communication, technical communication, graphic design and visualisation specialists as relevant | Help people understand the project and the decisions it needs. Agree audience, purpose and technical review with the people supplying the facts. |
| People, development and continuity | Delivery and functional leaders, HR/recruitment partners, mentors and sourcing support | Plan capability, capacity, mobilisation, onboarding, development and succession. Make time for learning and handover as well as the immediate assignment. |
Assign responsibilities across the company boundaries
Two organisations may each supply a project manager, design lead or planner. Start with a real decision, such as releasing a package for purchase or accepting a system for testing. Name who prepares the recommendation, supplies the evidence, checks it and approves it. Record the limits of delegated authority and the escalation route.
Walk the agreement through with the people expected to use it. Check that the owner, designer, contractor and operator have compatible assumptions about scope, information and acceptance. A responsibility matrix needs the same understanding in the meeting as it has on paper.
Find and assess talent before the gap becomes urgent
Translate a vacancy into the work the person must be able to perform. A scheduler might need to challenge delivery logic with construction leads; a design coordinator might need to resolve a supplier interface; a document controller might need to manage review and approval through several organisations. Those tasks give a more useful basis for assessment than the title alone.
- Agree job-related assessment criteria with the functional lead and recruitment partner before meeting candidates.
- Use a realistic, proportionate work scenario to explore assumptions, judgment, communication and when the candidate would seek specialist help.
- Assess both competence and capacity. Check when the person is available, what support they need and which competing assignments could prevent delivery.
- Plan onboarding around the project's decisions, tools, interfaces and reporting cycle, with a named person to help the newcomer become effective.
Ahmed's warning that a short interview reveals only part of how someone will work is a reason to support people after appointment as well as assess them before it.
Make the culture part of the delivery work
The director helps establish how people ask for help, challenge an assumption and raise bad news. Make the desired behaviour visible in ordinary work: listen when someone identifies an interface problem, agree the next action and show that early escalation produces support rather than blame.
Constructive teamwork still needs challenge. People must be able to flag a problem before they know the solution. Agree communication preferences, decision routes and feedback routines, then check whether quieter specialists and people from partner organisations can use them. A single team identity needs practical agreements about authority and interfaces.
Give capable people a reason to stay and grow
Ask each person how they weigh progression, meaningful work, compensation, security and workload. Use their answer to shape the development conversation.
- Agree development goals tied to real responsibilities, with coaching and feedback from someone able to support them.
- Make mentoring and knowledge transfer part of the capacity plan. Learning cannot depend entirely on spare time after delivery work.
- Be clear about assignment duration, likely next steps and what remains uncertain. Avoid promises the project cannot control.
- Identify critical knowledge held by one person, provide cover and prepare a handover before a phase change or departure.
Change the team as the project moves into the field
Revisit the capability plan at phase transitions. During definition, the team needs to settle requirements, uncertainty and the delivery approach. During design and procurement, it needs to coordinate interfaces and commitments. Construction needs executable work, supervision and access. Commissioning needs testing and acceptance capability; the operating organisation needs people, procedures and reliable asset information.
Plan the overlaps. Construction expertise is useful before site execution, and operational knowledge is useful before handover. Keep enough design and supplier support available to resolve field issues. At each transition, identify what the receiving team needs, who accepts it and which skills must stay until outstanding work is resolved.
Worked example: a critical equipment delivery slips
AACE's public overview describes the connections between cost engineering practices across a project's life cycle. The useful application here is integration: an estimate, a schedule and a risk assessment need a compatible basis before their outputs can support one decision. Producing each successfully in isolation does not establish that the combined forecast is coherent.
Imagine a supplier warns that a critical equipment delivery will be late. Follow the issue across the team to see what each role contributes:
- Establish the facts. Procurement checks the supplier's commitment and recovery options. Engineering checks whether design information or technical approval is holding up manufacture.
- Work out the consequences. Planning assesses the effect on installation and testing. Construction and commissioning examine practical alternatives. Cost and commercial specialists assess the forecast and contractual implications, while risk specialists help test the remaining uncertainty.
- Recommend and decide. Project controls brings the assessments together on a consistent basis. Project leadership coordinates the recommendation and approves within its authority, or takes the decision to the authorised sponsor or governance body.
- Act and confirm. Assign named owners and dates to the agreed actions. Source owners validate the revised information; reporting communicates the decision and its basis. Follow up to confirm that the promised recovery happened.
Agree package identifiers, scope boundaries, dates and change assumptions across those contributions. The data lead helps make information comparable, but source owners still need to validate what it means. A dashboard cannot resolve conflicting accountabilities or make incompatible reporting periods comparable by displaying them together.
Quick reference: roles people often mix up
Compare the purpose of the work before comparing seniority or reporting lines. These functions can sit together or in separate teams. Clarifying the boundary is more useful than insisting everyone adopt the same job title.
Scroll sideways or use the arrow keys to see all columns.
| Roles or functions | A useful distinction | Clarify on your project |
|---|---|---|
| Project manager and project controls | Project management coordinates delivery and decisions within delegated authority. Controls develops and tests the integrated picture of progress, cost, schedule, risk and change that informs those decisions. | Who produces the forecast, who challenges it, and who can authorise the response? |
| Project controls and the PMO | Controls is a set of performance management practices. A project management office is an organisational arrangement that may provide governance, methods, support and controls. Its remit can cover one project or a wider set of investments. | Does this PMO run controls, set the methods, provide assurance, or combine these services? |
| Planner and scheduler | Planning establishes how the work will be delivered. Scheduling models activities, dependencies, durations and dates. The work is closely connected, and the same person or job title often covers both. | Who develops the delivery sequence, maintains the schedule and validates progress with the people doing the work? |
| Cost estimator and cost controller | Estimating develops a cost expectation and its basis. Cost control tracks performance and changes, and updates the forecast against an agreed baseline. They work together throughout delivery. Cost engineering is a broader field that can include both. | Who owns the estimate assumptions, and who reconciles actuals, commitments and remaining work in the forecast? |
| Risk manager and risk owner | The risk manager facilitates the process and helps assess uncertainty. A named risk owner is accountable for managing a particular risk; response actions may be assigned to other people. Maintaining a register does not transfer every risk to its administrator. | Who owns this risk, who will perform each response action, and who can authorise the resources? |
| Procurement and contracts management | Procurement connects the buying strategy and supplier selection to delivery needs. Contracts management addresses obligations, administration and changes across the agreement's life. Their work overlaps before and after award. | Who agrees supplier commitments, administers changes and checks that the receiving team can use what is purchased? |
| Sponsor and owner representative | Sponsorship connects the project to its investment purpose and governance. An owner representative acts for the owner within a defined remit. That person may also be the sponsor, but the title does not establish investment approval authority. | Who is accountable for the investment purpose, and what may this representative approve on the owner's behalf? |
| Commissioning and operations readiness | Commissioning verifies and demonstrates that systems perform as intended. Operations readiness prepares the people, procedures, maintenance arrangements and support needed to operate them. The teams need an agreed handover. | Who accepts the system, and who confirms that the operating organisation is ready to take responsibility? |
The same caution applies to project director and project manager. A director may oversee a larger delivery scope or lead several managers, but the title does not establish a universal hierarchy. Ask what scope each person owns, which decisions are delegated and how unresolved issues are escalated.
How this map relates to industry role frameworks
There are established role frameworks to draw on. The UK Government Project Delivery Capability Framework gives government teams a common language for leadership and specialist roles, while recognising differences in local titles. Its scope helps explain governance and delivery responsibilities; a capital project's engineering, construction and operating teams still need their own clear arrangements.
APM's example profiles connect typical responsibilities with relevant competences and allow organisational adaptation. Use them alongside the project's governance and delivery model when shaping roles.
The director's team-readiness checklist
Follow the work into the next guide
Use the Data and Reporting guides to establish how the team will share trustworthy information and explain decisions. Use the Risk guide and workshop to bring the relevant people into uncertainty and response planning. Procurement guidance connects commercial choices to the needs of the receiving team. The audience tags help you find the next guide for the work you lead.
This field guide's Bookshelf
Explore the sources behind this article and related reading from our Bookshelf.
The Teal Book, Chapter 32: Solution design
Government Project Delivery Function · Referenced by PodBOK
Why it's on the shelfThe chapter distinguishes responsibility for the overall design from component design and explains how design methods, requirements and interfaces fit together. It recognises that design leadership titles vary by solution and discusses design authorities for complex work. This helps a director identify design capability beyond the management and controls team.
Referenced in this field guide Give design and engineering real ownership.
What is project team management and leadership?
Association for Project Management · Referenced by PodBOK
Why it's on the shelfAPM connects effective teamwork with understanding individual capabilities, expectations and team relationships. It describes leadership that adapts to the people and the work, and highlights vision, direction, feedback and support. This provides a basis for considering culture alongside technical capability when forming a project team.
Referenced in this field guide Make the culture part of the delivery work.
Total Cost Management (TCM) Framework
AACE International · Referenced by PodBOK
Why it's on the shelfAACE describes a process framework connecting estimating, planning, scheduling, cost control, forecasting, performance measurement and risk management across the life cycle of projects and assets. Its emphasis on relationships between practices helps explain why specialist contributions must be integrated into a consistent project picture.
Referenced in this field guide Worked example: a critical equipment delivery slips.
What is project controls?
Association for Project Management · Referenced by PodBOK
Why it's on the shelfAPM explains how controls brings measurement, forecasting and corrective-action analysis into project management. Its overview also recognises that project size and complexity affect who performs this work. It supports distinguishing the analytical contribution from locally assigned decision authority.
Referenced in this field guide Quick reference: roles people often mix up.
What is a PMO?
Association for Project Management · Referenced by PodBOK
Why it's on the shelfAPM describes a PMO as an organisational structure supporting projects, programmes or portfolios. Its services can include controls and reporting, and its location can vary. This helps explain why a PMO and project controls can overlap without being interchangeable terms.
Referenced in this field guide Quick reference: roles people often mix up.
APM glossary of project management terms
Association for Project Management · Referenced by PodBOK
Why it's on the shelfThe glossary provides a vocabulary for separating the risk management process from ownership of an individual risk, and for discussing project management and sponsorship. These definitions help teams compare functions before agreeing responsibilities in their own organisation.
Referenced in this field guide Quick reference: roles people often mix up.
Project delivery capability framework
Government Project Delivery Function · Referenced by PodBOK
Why it's on the shelfThe UK government framework provides a shared vocabulary for project delivery roles and competencies across projects, programmes and portfolios. Its public index distinguishes leadership, delivery specialists, and business analysis and change roles. It also recognises that job titles can differ between organisations.
Referenced in this field guide How this map relates to industry role frameworks.
APM Competence Framework: Example Role Profiles
Association for Project Management · Referenced by PodBOK
Why it's on the shelfAPM's example profiles connect typical responsibilities with relevant competences at different levels. The public guidance explains that profiles can share competences and be adapted to organisational needs. This supports discussing the work a role performs while allowing for differences in titles and team structure.
Referenced in this field guide How this map relates to industry role frameworks.
Keep exploring
Bibliography
Explore the conversations, publications and reading behind this field guide.
Podcast conversations
-
Conversation with Ahmed AbdelSalam
Passages and links
-
Define the work and delivery model before filling positions
Ahmed AbdelSalam
Ahmed AbdelSalam starts resource planning with project size, complexity, scope, roles and responsibilities. He then considers when people are needed and whether to hire, transfer people internally, bring in specialists or outsource a scope of work. The decision depends on the capability the client already has and the work it must manage.
-
Build the talent pipeline before the vacancy arrives
Ahmed AbdelSalam
AbdelSalam describes maintaining a professional network and talking with potential candidates before a role opens. When assessing technical capability, he asks how people would tackle real work and the challenges they have encountered. He explicitly says the continuous sourcing practice is especially a responsibility for HR and talent acquisition teams.
-
Make raising a problem the start of working on it together
Ahmed AbdelSalam
AbdelSalam puts responsibility for team culture on its leadership: people should help one another, flag problems and work on them together rather than point fingers. He also cautions that a short interview cannot reveal everything about how someone will work in the team.
-
Give people a credible path beyond the immediate assignment
Ahmed AbdelSalam
Describing his doctoral research, AbdelSalam says career growth came ahead of financial reward in the responses he studied. He connects that discussion to progression and job security. This is his reported finding from a particular study; the underlying thesis has not been independently reviewed for this guide.
-
-
Conversation with Jovita Stander
Passages and links
-
Make room for the specialists who make the information usable
Jovita Stander
Jovita Stander describes having GIS and graphic design specialists alongside project controls on Green Riyadh. The designers helped turn project information into presentations and park brochures for stakeholders. This was the arrangement she experienced on that programme, not a requirement that every controls team have the same reporting lines.
-
Let the asset determine the specialist knowledge you need
Jovita Stander
Stander describes Green Riyadh's tree management office working with a specialist company whose resources included landscape engineers, GIS staff and technical staff. Selecting and managing green assets needed expertise specific to an urban forest, alongside the wider programme management functions.
-
-
Conversation with Leanne Allgaier
Passages and links
-
Give controlled information a clear owner
Leanne Allgaier
Allgaier argues that document control needs people who understand a document's lifecycle, including review, change, approval and distribution. She describes organisational arrangements that give these specialists access to the technical people using and approving the information, while noting that reporting lines vary.
-
-
Conversation with Ellie Moradinezhad
Passages and links
-
Make the team's decision rights explicit
Ellie Moradinezhad
Moradinezhad describes defining who is consulted, informed, deciding and acting, with authority and escalation matched to the project. Her collaborative-delivery examples show why a team still needs clear boundaries between the owner, designers and construction participants.
-
-
Conversation with Tarun Gohel
Passages and links
-
A signed requirement still needs a shared understanding
Tarun Gohel
Gohel recalls a failure to train contractors on project controls requirements included in their contracts. He recommends explaining the requirements together at kickoff, connecting commercial documentation with the people expected to use it.
-
-
Conversation with James Wiseman
Passages and links
-
Lead the team as a coach
James Wiseman
Wiseman describes a project manager or director helping a capable team move towards its goal. He follows this with practical advice about agreeing communication preferences, making milestones clear and ensuring people have the plan and tools to execute. Giving people room to work still requires active project leadership.
-
-
Conversation with Matt Mitchell
Passages and links
-
Risk management needs a facilitator
Matt Mitchell
Mitchell describes making room for quieter participants in a risk workshop. The risk lead helps the team surface its knowledge; accountable owners still need to act on the risks.
-
-
Conversation with Geoff Ryan
Passages and links
-
The receiving team needs executable work
Geoff Ryan
Ryan describes installation work packages that foremen can execute because constraints have been removed. His construction background connects the planning output to the people who receive it in the field.
-
Publications and further reading
-
The Teal Book, Chapter 32: Solution design
Government Project Delivery Function · Cited source
Publication details
The Teal Book, version 3.0; chapter updated July 1, 2026
Sections 32.4-32.5; 32.6.1.1; 32.6.1.3; 32.6.2.3-32.6.2.4.
Chapter 32 concerns UK government project delivery, including its formal accountability model.
-
What is project team management and leadership?
Association for Project Management · Cited source
Publication details
Public topic overview drawing on APM Body of Knowledge, 8th edition
Definition; Teams and leaders; Four key skills for successful project leadership.
The source is APM's public topic overview, separate from the complete Body of Knowledge and teamwork guide.
-
Total Cost Management (TCM) Framework
AACE International · Cited source
Publication details
Living online framework; public publisher overview
Framework introduction; What Is the Total Cost Management Framework?; How the Total Cost Management Framework Integrates with Cost Engineering Practices.
This source is the publisher's overview; the complete framework is available separately.
-
What is project controls?
Association for Project Management · Cited source
Publication details
Public topic overview; no numbered edition stated
Core elements; Who is responsible for project controls.
This source is APM's public topic overview, separate from its longer project-controls publication.
-
What is a PMO?
Association for Project Management · Cited source
Publication details
Public topic overview drawing on APM Body of Knowledge, 8th edition
Definition; types of PMO; benefits and services.
The source is APM's public overview. Embedded, central and combined PMOs are examples whose responsibilities vary by organisation.
-
APM glossary of project management terms
Association for Project Management · Cited source
Publication details
Living public glossary; entries draw on several editions and publications
Risk manager; Risk owner; Sponsor; Project manager; Project management office entries.
The glossary draws terminology from several Body of Knowledge editions and other publications.
-
Project delivery capability framework
Government Project Delivery Function · Cited source
Publication details
Current online framework; page published June 10, 2025
Framework introduction; role families and roles; guidance on job titles.
The source is the UK government framework introduction and role index. The guide's capability map is a general model for major projects.
-
APM Competence Framework: Example Role Profiles
Association for Project Management · Cited source
Publication details
Competence Framework, 3rd edition; example role profiles
How to use the APM Competence Framework: Role profiles; introduction to PMO Officers and Specialists profile.
The cited material introduces example role profiles within APM's wider competence framework.
Source context
The capability map is a general model. Jovita Stander describes selected teams and reporting relationships specific to Green Riyadh.
Ahmed AbdelSalam's networking example illustrates a talent pipeline. His reported development study describes participants' priorities, which can differ between people.
PodBOK · The Major Project Podcast
https://www.themajorprojectpodcast.com/podbok/major-project-roles · Updated 2026-11-01