101: give the model a job
Building Information Modelling (BIM) brings structured information about an asset into the way people design, build and operate it. On a major project, that might connect a pump to its location, specification, installation package, cost allowance and maintenance record. The visible model helps people understand those relationships. The information and the delivery process make them useful.
Start by asking what somebody will do differently with the information. A construction manager may need to test access for a lift. An estimator may need quantities for a package. An operator may need to identify the installed equipment and retrieve its maintenance instructions. Each use requires different detail, different checks and a different moment of delivery.
A federated model brings the relevant discipline models together for review while each team remains responsible for its contribution. It helps people inspect interfaces across boundaries. Someone still needs to decide which revisions belong in the review, who resolves the conflicts and when the resulting information is ready to use.
Implementation: specify the decisions and information
The useful distinction is between organizational information requirements (OIR), asset information requirements (AIR), project information requirements (PIR) and exchange information requirements (EIR). These connect the owner’s wider needs to what a particular delivery team must supply. Agree the requirements before appointing that team, including the purpose, recipient, timing and acceptance check.
Make one exchange concrete. For a hypothetical pump package, the maintenance lead needs the equipment tag, installed location, manufacturer and manual before accepting the asset record. The construction team may also need the lifting envelope earlier. Specify the geometry, properties and documents needed for each use. A request for a highly detailed model leaves too much for the recipient to guess.
Scroll sideways or use the arrow keys to see all columns.
| Use | Decision | Information to agree |
|---|---|---|
| 3D coordination | Can the designed systems fit and be maintained? | Interfaces, clearances, coordinates and design revisions. |
| 4D planning | Can this sequence be built with the available access and resources? | Model-to-activity links, dates, temporary works and work areas. |
| 5D cost planning | What does this scope cost, and what changed? | Measured quantities, classification, rates, scope boundaries and assumptions. |
Ask the receiving team to approve a small example before the supplier models the whole package. A pump, a room or a short section of pipe is enough to expose different interpretations of names, units and required properties.
Implementation: put people and delivery dates in the plan
Write a BIM execution plan that the team can use in its weekly work. Describe the agreed model uses, responsibility boundaries, software exchanges, review cycle and handover deliverables. Assign an owner to each decision. The person coordinating models needs access to the people who can change the design, schedule and construction method.
Scroll sideways or use the arrow keys to see all columns.
| Responsibility | Decision to own |
|---|---|
| Owner and operator | What information is needed and what constitutes an acceptable delivery. |
| Design leads | Technical content and interfaces within and between disciplines. |
| Information or BIM manager | Delivery rules, coordination workflow and information checks. |
| Planner and construction team | Activity links, sequence, access and field progress. |
| Estimator and cost team | Quantity rules, rates, scope coverage and change reconciliation. |
| Document control | Issue, revision, suitability, distribution and retained records. |
Bring the package delivery dates into the project calendar. A model needed for a procurement decision must arrive early enough for checking and correction. Set a submission cutoff, review window and release date. Keep a list of missing packages and late responses visible alongside the combined model.
Walk the process with a subcontractor. Have them submit a sample, receive an issue, correct it and find the accepted revision. That short exercise tests access and understanding before the first major coordination meeting.
Implementation: make objects connect across systems
A component can appear in a design model, a schedule, an estimate, a purchase order and an asset register. Agree how those records connect. Give objects stable identifiers, define classification and location codes, and document the mapping to work packages and cost accounts. A change to a display name should not silently create a new asset.
Avoid forcing every system into one enormous code. A model object may relate to several activities, such as fabrication, delivery, installation and testing. A schedule activity may cover several objects. Keep those relationships explicit, including who maintains them when scope splits, packages move or objects are replaced.
Test an exchange through the actual tools: export a representative package, open it in the receiving application and check identifiers, quantities, properties, units and position. Record what survives and what needs a separate mapping. Make the agreed exchange format and version part of the delivery plan.
For a warehouse or reporting layer, carry the model revision and issue status with each extract. Reconcile objects added, removed or changed before loading the next period. Preserve the earlier accepted extract so a changed design does not silently rewrite last month’s report.
Implementation: control what people are allowed to use
The common data environment (CDE) combines the agreed workflow and supporting systems. Work in progress belongs to its producing team. Shared information is available for an agreed purpose. Published information has passed the required authorization and acceptance. The archive retains the history of exchanges and decisions. Revision and suitability are separate questions: which version is this, and what may I use it for?
Run a practical access test with a field supervisor: find the current package, establish its permitted use and see what changed. Then try the same task with a superseded download. Make the status visible enough that the wrong copy is easy to recognize.
Control access by responsibility and information sensitivity. Agree who can release a package, who can accept it and how a superseded issue is withdrawn from active use. Keep the supporting review and transmittal records with the release. Document-control discipline needs to follow the model into the field.
Advanced practice: use 4D to challenge the plan
Use 4D to rehearse the work with the people who will deliver it. Show the proposed sequence, pause at a difficult interface and ask what must be true for the next operation to happen. Bring construction, planning, logistics, temporary works and the affected trades into that discussion.
- Test access and working space: deliveries, laydown, lifting positions, escape routes and maintenance of operating facilities.
- Show temporary conditions as well as the finished asset: scaffolding, excavations, temporary supports and equipment movements.
- Compare a proposed recovery with the baseline and current forecast. Record the changed crew, productivity and access assumptions.
- Give each decision an owner and due date, then update the plan and the model together.
More crews only help where there is workable space and supporting capacity. A visual scenario can expose congestion, but the team still needs to check the engineering, productivity and safety assumptions behind it. Let the construction specialists challenge the simulation while those assumptions are visible.
Define progress states with the field team. Delivered, installed, inspected, tested and accepted describe different achievements. Check representative objects against site records before presenting a monthly progress model. Keep the baseline and current-period views identifiable so the audience knows what it is comparing.
Advanced practice: give quantities and cost a clear basis
For 5D, make the path from scope to quantity to cost traceable. The estimator should be able to select a cost line and identify the included objects, measurement rule, unit, rate basis and allowances. The design team should be able to change a package and see which quantities and assumptions need review.
Start with one package and reconcile it against the estimate. Check openings, overlapping objects, duplicate elements, excluded items and modelled boundaries. Agree how quantities are measured and when the model is sufficiently developed for that use. A precise geometry calculation can still represent the wrong commercial quantity.
Consider a pump whose geometry stays the same while the specification changes. Its purchase price, testing requirement or delivery date may change without a visible change in the model. Cost and schedule owners need to review those consequences; the model relationship helps them find the affected records.
Use the linked view to ask better questions at a change review. Which scope changed? Which procurement packages are exposed? Does the forecast include the latest approved design? Record the agreed answer and its supporting revision before updating the control baseline.
Advanced practice: check the information and close the issues
Separate information checks, geometric coordination and engineering review. A model may contain all required properties yet use the wrong design assumption. It may have no detected hard clashes while leaving insufficient working or maintenance space. Assign the checks to people qualified to judge each problem.
Begin automated checks with a few useful requirements: the agreed asset tag exists, the classification is valid, the required property has the expected unit, and mandatory values are present. Test the rules on deliberately incomplete examples. Keep engineering approval and site verification as explicit steps.
Make each coordination issue actionable: identify the objects and model revision, describe the conflict, assign the responsible party and set a response date. Record the proposed resolution and have the affected discipline confirm it. Close the issue after checking the revised information, with evidence of the decision.
Review the issues that threaten an upcoming decision or installation window first. A low total clash count tells little about the severity of the remaining conflicts. Track overdue decisions, repeat problems and issues reopened after a new revision so the team can see where coordination is breaking down.
Test a real model-to-drawing handoff with the people preparing the work. Can they connect the drawing revision, required materials and installation package without rebuilding the information by hand? Record missing links as delivery issues and assign an owner before the package reaches the field.
Implementation: rehearse handover while the team is still there
Invite the operator to test an asset package early. Can a maintenance planner find the installed equipment, identify its location, retrieve the correct manual and see the inspection or commissioning record? Can the receiving asset system import the agreed fields without somebody rebuilding them by hand?
Agree the handover acceptance checks alongside the asset information requirements. Include installed identifiers, approved changes, equipment details, linked records and outstanding defects. Keep clear distinctions between the design intent, the installed condition and information that still needs verification.
Trial the transfer with a representative package well before final handover. Check links after moving the files, access after contractor accounts close, and whether the operator can maintain the information. Assign responsibility for corrections and for subsequent changes to the asset record.
A model becomes a continuing asset only when someone owns its upkeep. Decide which information will be maintained in the model, which belongs in operational systems and how those records stay connected. Avoid leaving the operator with two competing versions of the same equipment history.
Advanced practice: build a reliable view before automating it
Use the model as one way to explain a decision. In a progress review, show the affected area, the variance, the consequence and the action needed. Keep a simple legend and pause long enough for the construction team to examine the evidence. The reporting guide develops this approach to attention and visual storytelling.
Preserve the model, schedule and cost versions used for a decision. When reviewing an option later, the team needs to reconstruct the information available at the time. A current view and an approved period view serve different purposes; give each a clear date and owner.
AI can help draft issue summaries, suggest classifications or flag missing properties. Start with bounded tasks that can be checked against an approved dataset. Show the source objects and revision, record corrections and keep the release decision with the responsible person. Use the AI guide to plan evaluation, permissions and review.
Measure whether the work is helping: fewer repeated coordination issues, accepted exchanges arriving before decisions, and shorter time spent finding the right information. Review those observations with the users and adjust the model scope. Add detail when it supports a real use.
Lessons from the field: start with one useful delivery
A practical first month can establish a working pattern. Choose a package with a real upcoming decision, a willing delivery team and a manageable set of interfaces. Keep the scope small enough to run the full cycle, from requirements to accepted information.
At the end, ask the project director, planner and construction lead to show a decision that became clearer. Ask the delivery team which requirement caused unnecessary work. Use both answers to improve the next cycle. The goal is a repeatable way of delivering information that people can act on.
This field guide's Bookshelf
Explore the sources behind this article and related reading from our Bookshelf.
ISO 19650-1:2018: Information management using building information modelling, Part 1: Concepts and principles
International Organization for Standardization (ISO) · Referenced by PodBOK
Why it's on the shelfISO describes a framework for organizing, exchanging and maintaining information across a built asset's lifecycle. It provides context for connecting document control to the wider information-management process, rather than treating it as file storage.
Referenced in this field guide 101: give the model a job.
Guidance Part D: Developing information requirements
UK BIM Framework (guidance now hosted by the IMI Framework) · Referenced by PodBOK
Why it's on the shelfThe guidance connects business and asset needs to specific information exchanges. It separates geometry, data and documents so teams can ask for the information needed for a defined purpose.
Referenced in this field guide Implementation: specify the decisions and information.
Industry Foundation Classes (IFC): An Introduction
buildingSMART International · Referenced by PodBOK
Why it's on the shelfIFC is an open data model for exchanging information about built assets. It carries object identity, properties and relationships, giving different applications a shared structure for the information they exchange.
Referenced in this field guide Implementation: make objects connect across systems.
Guidance Part C: Facilitating the common data environment (workflow and technical solutions)
UK BIM Framework (guidance now hosted by the IMI Framework) · Referenced by PodBOK
Why it's on the shelfThe guidance describes a common data environment as a managed workflow supported by technology. Information moves through controlled states, while revision and suitability metadata tell recipients what they may use.
Referenced in this field guide Implementation: control what people are allowed to use.
Information Delivery Specification (IDS)
buildingSMART International · Referenced by PodBOK
Why it's on the shelfIDS lets teams express information requirements in a form that software can check against an IFC dataset. It helps turn required properties and classifications into repeatable delivery checks.
Referenced in this field guide Advanced practice: check the information and close the issues.
BIM Collaboration Format (BCF): An Introduction
buildingSMART International · Referenced by PodBOK
Why it's on the shelfBCF allows teams using different BIM applications to exchange model issues with the relevant viewpoints and object references. The issue can travel with its context instead of being reduced to an isolated screenshot.
Referenced in this field guide Advanced practice: check the information and close the issues.
ISO 19650-3:2020: Information management using building information modelling, Part 3: Operational phase of the assets
International Organization for Standardization (ISO) · Referenced by PodBOK
Why it's on the shelfISO 19650-3 addresses information management and exchanges during asset operation. It gives handover a continuing purpose: information that an operator can maintain and use throughout the asset’s working life.
Referenced in this field guide Implementation: rehearse handover while the team is still there.
Keep exploring
Bibliography
Explore the conversations, publications and reading behind this field guide.
Podcast conversations
-
Conversation with Omar Habib
Passages and links
-
Connect the model, schedule and cost plan
Omar Habib
Habib explains 4D through time and 5D through cost. He points out that projects often establish budgets before detailed models exist, then connect the information as the project develops.
-
Decide what the model is for
Omar Habib
Habib starts a 4D exercise at a whiteboard: who will use it, for what purpose, how often it will be updated, and what information goes in and comes out. He distinguishes a presentation model from one used to calculate quantities.
-
Agree the codes and calendar with every package
Omar Habib
Describing coordination across 66 subcontractors, Habib explains how his team agreed model codes, shared parameters, activity IDs, upload expectations and a review calendar at the start. Regular reviews then checked whether each package followed that agreement.
-
Translate between the disciplines
Omar Habib
Habib describes workshops bringing commercial, procurement, project controls, engineering and BIM teams together. Knowing how each discipline describes its work helps him agree the identifiers and information they need to exchange.
-
Use the simulation to test the construction plan
Omar Habib
Habib describes construction teams reviewing the sequence together and testing changes to crews and packages in the room. The discussion connects the visual plan to practical choices about how the work will happen.
-
Take the model back to the field
Omar Habib
Habib recalls a review where the simulation showed facade work installed while the construction team said it was not on site. He describes using site evidence and a feedback loop to resolve different interpretations of progress and completion.
-
Start with the coordination problem that matters now
Omar Habib
Habib describes a project rescue that focused on a critical coordination issue and a short simulation effort. The immediate result was clearer visibility and communication so stakeholders could act.
-
-
Conversation with AJ Waters
Passages and links
-
Keep people connected to the current approved information
AJ Waters
Waters uses a drawing revision to explain why project information changes. He argues that people need access to the relevant updated drawings, change orders and RFIs, because different versions can lead to conflict and rework.
-
-
Conversation with Grant Stead
Passages and links
-
Make model information usable at the drawing level
Grant Stead
Grant Stead describes a project where the engineering team could not supply a complete material takeoff by isometric drawing. He connects the difficulty to how drawings are exported from the model and the manual work still needed. Construction needs information it can use against the actual drawing and work package.
-
Publications and further reading
-
ISO 19650-1:2018: Information management using building information modelling, Part 1: Concepts and principles
International Organization for Standardization (ISO) · Cited source
Publication details
Edition 1, December 2018; confirmed in 2024; revision in development
Public abstract, publication status and linked revision notice.
The source is the public abstract for ISO 19650-1:2018. It introduces information-management concepts without prescribing a universal status-code scheme or software configuration.
-
Guidance Part D: Developing information requirements
UK BIM Framework (guidance now hosted by the IMI Framework) · Cited source
Publication details
Edition 2, February 2021
Sections 1.3 to 1.6 and 2: organizational, asset, project and exchange information requirements; level of information need.
This 2021 UK implementation guidance explains information-requirements concepts; it is separate from the full ISO standards.
-
Industry Foundation Classes (IFC): An Introduction
buildingSMART International · Cited source
Publication details
Public technical introduction; ISO 16739-1:2024 identified by the publisher
What is IFC? and How is IFC used?
This technical introduction explains the IFC data model. An actual exchange also depends on export settings and the applications involved.
-
Guidance Part C: Facilitating the common data environment (workflow and technical solutions)
UK BIM Framework (guidance now hosted by the IMI Framework) · Cited source
Publication details
Edition 1, September 2020
Sections 1 and 2, Figure 2; sections 5 and 6: workflow, revision control and status metadata.
The publication's specific status codes come from the UK National Annex. Other projects may use different agreed codes.
-
Information Delivery Specification (IDS)
buildingSMART International · Cited source
Publication details
IDS 1.0; final standard announced 4 June 2024
Official repository README and user manual; publisher announcement of IDS 1.0 final status.
IDS checks information requirements. Engineering and geometric review remain separate checks.
-
BIM Collaboration Format (BCF): An Introduction
buildingSMART International · Cited source
Publication details
Public technical introduction; BCF XML and API implementations
What is BCF? and How is BCF used?
BCF supports issue exchange; the format does not itself resolve a coordination issue.
-
ISO 19650-3:2020: Information management using building information modelling, Part 3: Operational phase of the assets
International Organization for Standardization (ISO) · Cited source
Publication details
Edition 1, July 2020; confirmed in 2024; replacement drafts in development
Public abstract, publication status and replacement notices.
The source is the public abstract for ISO 19650-3:2020, which concerns information management during asset operation.
From the knowledge library
The dimension stack is an on-ramp, not a ladder
Original card context
From the Lego-house explainer (~11:30) and the 5D-before-3D exchange (~15:45–17:00)
“What’s true today is not necessarily true tomorrow. A perfect example is a drawing revision.”
Original card context
AJ Waters · ~40:00 · ep 027 with AJ Waters
Source context
Omar Habib uses 6D to mean sustainability. Dimensional labels beyond 3D, 4D and 5D vary across organisations and do not form an ISO maturity scale.